Common use of Eligible Changes Clause in Contracts

Eligible Changes. This section outlines when Design-Builder shall submit a Change Notice and Request for Change Order to VPRA. Design-Builder shall use this process to request an adjustment to the Contract Price or a Completion Deadline due to a Relief Event. All Relief Events are subject to the limitations stated in this Article 12 in addition to any limitations stated in the definition of each Relief Event or elsewhere in the Contract Documents. Other than for the Relief Events herein, Design-Builder shall not be entitled to any adjustment of the Contract Price or a Completion Deadline. With respect to any request for relief, Design-Builder shall bear the burden of proving that it is entitled to the relief sought.