Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs. ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt. v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date. vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies. vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan. viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services. ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause. x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 15 contracts
Sources: Rate Contract, Rate Contract for Supply, Installation, Commissioning and Maintenance of GPS Devices, Rate Contract for Supply, Installation, Commissioning and Maintenance of GPS Devices
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following Rate Contract for Selection of Logistic Partner for e-Bazaar aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.. Rate Contract for Selection of Logistic Partner for e-Bazaar
Appears in 2 contracts
Sources: Rate Contract for Selection of Logistic Partner, Rate Contract
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; andand Rate Contract for Selection of Logistic Partner for e-Bazaar
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.. Rate Contract for Selection of Logistic Partner for e-Bazaar
Appears in 2 contracts
Sources: Rate Contract for Selection of Logistic Partner, Rate Contract for Selection of Logistic Partner
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.. Rate Contract for Setting up of Interactive Digital Amusement Gallery during various events
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Sources: Rate Contract
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. iv. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. v. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
viivi. In the event of expiry and termination of contract or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viiivii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ixviii. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. ix. It would be the responsibility of the selected bidder to support new operator operator, if any, during the transition period.. Rate Contract for Proc. of MS-Exchange Server Licenses, Device CALs including Support Services
Appears in 1 contract
Sources: Rate Contract
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.. Rate Contract for Supply, Installation, commissioning and FMS of Edge equipment’s under Surveillance and Incident Response Project in the State of Rajasthan (After Pre-bid)
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Sources: Rate Contract for Supply, Installation, Commissioning and FMS of Edge Equipment
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material Rate contract for Printing and Delivery of PVC Cards and other documents (After Pre-Bid) detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Sources: Rate Contract
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.. Rate Contract for Supply, installation and commissioning of additional Edge equipment’s under Surveillance and Incident Response Project in the State of Rajasthan (After Pre-bid)
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Sources: Rate Contract for Supply, Installation and Commissioning
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.. Rate Contract for Various Surveillance items to be deployed in the State of Rajasthan
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure the continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for the provision of contingent support in terms of business continuance and hand hand-holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of the contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs SOWs, each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support the new operator during the transition period.
Appears in 1 contract
Sources: Rate Contract for Supply of Usb Cryptographic Token
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following Final RFP-Rate Contract for Selection of Logistic Partner for e-Bazaar aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.. Final RFP-Rate Contract for Selection of Logistic Partner for e-Bazaar
Appears in 1 contract
Sources: Rate Contract for Logistic Partner
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.. Rate Contract for GPU based Workstations for WS&APS with Five Years O&M
Appears in 1 contract
Sources: Rate Contract for Gpu Based Workstations for Ws&aps With Five Years O&m
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material Rate contract for Printing and Delivery of PVC Cards and other documents (Before Pre-Bid) detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Sources: Rate Contract
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.. Rate Contract (After Pre-bid) for Various Surveillance items to be deployed in the State of Rajasthan
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Sources: Rate Contract
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing Rate Contract for Supply, Installation, commissioning and FMS of Edge equipment’s under Surveillance and Incident Response Project in the State of Rajasthan provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Sources: Rate Contract for Supply, Installation, Commissioning and FMS of Edge Equipment
Exit Management Plan. i. The selected bidder shall provide RISL DOA or its nominated agencies with a recommended exit management plan of 30 days ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL DoA or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. iv. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. v. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL DoA or its nominated agencies.
viivi. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs SoWs each party shall comply with the Exit Management Plan.Plan.
viiivii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ixviii. No Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clausemade.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Sources: Rate Contract
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.. Draft RFP-Rate Contract for Selection of Logistic Aggregator for e-Bazaar
x. It would be the responsibility of the selected bidder to support new operator during the transition period.
Appears in 1 contract
Exit Management Plan. i. The selected bidder shall provide RISL or its nominated agencies with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the SLA as a whole and in relation to the Project Implementation, the Operation and Management SLA and SOWs.
ii. A detailed program of the transfer process that could be used in conjunction with a replacement operator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; and
iii. Plans for the communication with such of the selected bidder's, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on RISL operations as a result of undertaking the transfer; and
iv. If applicable, proposed arrangements and Plans for provision of contingent support in terms of business continuance and hand holding during the transition period, to RISL or its nominated agencies, and Replacement Operator for a reasonable period, so that the services provided continue and do not come to a halt.
v. The Bidder shall re-draft the Exit Management Plan annually after signing of contract to ensure that it is kept relevant and up to date.
vi. Each Exit Management Plan shall be presented by the selected bidder to and approved by RISL or its nominated agencies.
vii. In the event of termination or expiry of SLA, Project Implementation, Operation and Management SLA or SOWs each party shall comply with the Exit Management Plan.
viii. During the exit management period, the selected bidder shall use its best efforts to deliver the services.
ix. Payments during the Exit Management period shall be made in accordance with the Terms of Payment Clause.
x. It would be the responsibility of the selected bidder to support new operator during the transition period.. Rate Contract for Supply of Digital Signature Certificates (with USB Tokens) and Server SSL Certificates
Appears in 1 contract
Sources: Rate Contract for Supply of Digital Signature Certificates and Server SSL Certificates