Extension of timeframes Sample Clauses

Extension of timeframes a. The Contractor may extend the timeframes for standard and expedited resolution of grievances and appeals by up to 14 calendar days if: i. The beneficiary requests the extension; or ii. The Contractor shows (to the satisfaction of the Department, upon its request) that there is need for additional information and how the delay is in the beneficiary’s interest.
Extension of timeframes. 9.7.2.1 The Contractor may extend the timeframes from §9.7.1 of this section by up to fourteen (14) calendar days if: 9.7.2.1.1 The member requests the extension; or 9.7.2.1.2 The Contractor shows (to the satisfaction of SCDHHS, upon its request) that there is need for additional information and how the delay is in the member's interest.
Extension of timeframes. The PIHP may extend the grievance resolution and notice timeframe by up to 14 calendar days if the Enrollee requests an extension, or if the PIHP shows to the satisfaction of the State that there is a need for additional information and how the delay is in the Enrollee’s interest. 42 CFR 438.408(c). a. If the PIHP extends resolution/notice timeframes, it must complete all of the following: 42 CFR 438.408(c) i. Make reasonable efforts to give the Enrollee prompt oral notice of the delay; ii. Within 2-calendar days, give the Enrollee written notice of the reason for the decision to extend the timeframe and inform the Enrollee of the right to file a Grievance if they disagree with the decision; and iii. Resolve the Appeal as expeditiously as the Enrollee’s health condition requires and not later than the date the extension expires
Extension of timeframes. The parties may extend the above described
Extension of timeframes. The Purchasers hereby grant a 30-day extension (i.e., for filing, to October 22, 2008, and for effectiveness, to January 20, 2009 or February 19, 2009, as applicable) of the timeframes set forth in Section 2 of the Registration Agreement (including the definitional terms therein), and no liquidated damages shall accrue during such 30-day period.
Extension of timeframes. The CCN may extend the timeframes from § 9.7.1 of this section by up to fourteen (14) calendar days if: a. The member requests the extension; or b. The CCN shows (to the satisfaction of DHH, upon its request) that there is need for additional information and how the delay is in the member's interest.
Extension of timeframes i. The PAHP may extend the timeframes from paragraph (b) of this section by up to 14 calendar days if 1. The enrollee requests the extension; or 2. The PAHP shows (to the satisfaction of the State agency, upon its request) that there is need for additional information and how the delay is in the enrollee's interest.
Extension of timeframes. The CONTRACTOR may extend the timeframes stated in this subsection of this contract by up to fourteen (14) Calendar Days if: The Medicaid Managed Care Member requests the extension, or The CONTRACTOR shows (to the Department’s satisfaction, upon its request) that there is need for additional information and how the delay is in the Medicaid Managed Care Member's interest. Requirements Following Extension: Make reasonable efforts to give the Enrollee prompt oral notice of the delay. Within two (2) Calendar Days give the Enrollee written notice of the reason for the decision to extend the timeframe and inform the Enrollee of the right to file a Grievance if he or she disagrees with that decision. Resolve the Appeal as expeditiously as the Enrollee’s health condition requires and no later than the date the extension expires.
Extension of timeframes. 9.6.2.1 The Contractor may extend the timeframes from § 9.7.1 of this Section by up to fourteen (14) calendar days if: 9.6.2.1.1 The Medicaid MCO Member requests the extension; or 9.6.2.1.2 The Contractor shows (to the Department’s satisfaction, upon its request) that there is need for additional information and how the delay is in the Medicaid MCO Member's interest.

Related to Extension of timeframes

  • Extension of Time Limits The time limits referred to in this Article may be extended by mutual agreement of the parties in writing.

  • Extension of Time If the Executive shall be in violation of any provision of this Article 6, then each time limitation set forth in this Article 6 shall be extended for a period of time equal to the period of time during which such violation or violations occur. If the Company seeks injunctive relief from such violation in any court, then the covenants set forth in this Article 6 shall be extended for a period of time equal to the pendency of such proceeding including all appeals by the Executive.

  • Extension of time for completion (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely: (a) delay in providing the Right of Way of Construction Zone, environmental clearances or approval of railway authorities, specified in Clause 3.1 (iv); (b) Change of Scope (unless an adjustment to the Scheduled Completion Date has been agreed under Article 13); (c) occurrence of a Force Majeure Event; (d) any delay, impediment or prevention caused by or attributable to the Authority, the Authority's personnel or the Authority's other contractors on the Site; and (e) any other cause or delay which entitles the Contractor to Time Extension in accordance with the provisions of this Agreement. (ii) The Contractor shall, no later than 15 (fifteen) business days from the occurrence of an event or circumstance specified in Clause 10.5 (i), inform the Authority’s Engineer by notice in writing, with a copy to the Authority, stating in reasonable detail with supporting particulars, the event or circumstances giving rise to the claim for Time Extension in accordance with the provisions of this Agreement. Provided that the period of 15 (fifteen) business days shall be calculated from the date on which the Contractor became aware, or should have become aware, of the occurrence of such an event or circumstance. Provided further that notwithstanding anything to the contrary contained in this Agreement, Time Extension shall be due and applicable only for the Works which are affected by the aforesaid events or circumstances and shall not in any manner affect the Project Completion Schedule for and in respect of the Works which are not affected hereunder. (iii) On the failure of the Contractor to issue to the Authority’s Engineer a notice in accordance with the provisions of Clause 10.5 (ii) within the time specified therein, the Contractor shall not be entitled to any Time Extension and shall forfeit its right for any such claims in future. For the avoidance of doubt, in the event of failure of the Contractor to issue notice as specified in this clause 10.5 (iii), the Authority shall be discharged from all liability in connection with the claim. (iv) The Authority’s Engineer shall, on receipt of the claim in accordance with the provisions of Clause 10.5 (ii), examine the claim expeditiously within the time frame specified herein. In the event the Authority’s Engineer requires any clarifications to examine the claim, the Authority’s Engineer shall seek the same within 15 (fifteen) days from the date of receiving the claim. The Contractor shall, on receipt of the communication of the Authority’s Engineer requesting for clarification, furnish the same to the Authority’s Engineer within 10 (ten) days thereof. The Authority’s Engineer shall, within a period of 30 (thirty) days from the date of receipt of such clarifications, forward in writing to the Contractor its determination of Time Extension. Provided that when determining each extension of time under this Clause 10.5, the Authority’s Engineer shall review previous determinations and may increase, but shall not decrease, the total Time Extension. (v) If the event or circumstance giving rise to the notice has a continuing effect: (a) a fully detailed claim shall be considered as interim; (b) the Contractor shall, no later than 10 (ten) days after the close of each month, send further interim claims specifying the accumulated delay, the extension of time claimed, and such further particulars as the Authority’s Engineer may reasonably require; and (c) the Contractor shall send a final claim within 30 (thirty) days after the effect of the event or the circumstance ceases. Upon receipt of the claim hereunder, the Authority’s Engineer shall examine the same in accordance with the provisions of Clause 10.5 (iv) within a period of 30 (thirty) days of the receipt thereof

  • Extension of Time; Waiver At any time prior to the Effective Time, the parties may, by action taken or authorized by their respective Boards of Directors, to the extent permitted by applicable Law, (a) extend the time for the performance of any of the obligations or acts of the other parties, (b) waive any inaccuracies in the representations and warranties of the other parties set forth in this Agreement or any document delivered pursuant hereto or (c) subject to applicable Law, waive compliance with any of the agreements or conditions of the other parties contained herein; provided, however, that after the Company Stockholder Approval has been obtained, no waiver may be made that pursuant to applicable Law requires further approval or adoption by the Stockholders without such further approval or adoption. Any agreement on the part of a party to any such waiver shall be valid only if set forth in a written instrument executed and delivered by a duly authorized officer on behalf of such party. No failure or delay of any party in exercising any right or remedy hereunder shall operate as a waiver thereof, nor shall any single or partial exercise of any such right or power, or any abandonment or discontinuance of steps to enforce such right or power, or any course of conduct, preclude any other or further exercise thereof or the exercise of any other right or power. The rights and remedies of the parties hereunder are cumulative and are not exclusive of any rights or remedies which they would otherwise have hereunder.