Factory Acceptance Test. (FAT) – Every davit fabricated under this solicitation shall undergo a Factory Acceptance Test. The vendor shall produce a test procedure (CDRL A004) that includes detailed test procedures, schedules, test installation layout, location, duration, and required test instrumentation and equipment. Test procedures shall require Government approval. The Contractor Factory Acceptance Test procedure shall ensure that all hardware components and operating system work as an integrated system and include the following tests in accordance with NAVSEA Drawing 583-6743681 Rev B. The contractor shall notify the government no later than 7 days prior to the start of testing (CDRL A013). For Factory Acceptance Testing the number of cycles shall be performed for the following tests: (1) 200% Static Load Test (2 cycles)