Factory Acceptance Testing. Company is responsible for the development of the factory acceptance test plan ("FATP") for the Products. The FATP must be submitted to Motorola for review and approval or comments four (4) weeks prior to the planned start of acceptance testing for Products to be delivered to Motorola under this Agreement. Motorola must provide its comments concerning the FATP, if any, within two (2) weeks and the FATP must be approved by both Parties, which approval shall not be unreasonably withheld, prior to the start of Product factory acceptance testing. The FATP will be a subset of Company's standard product verification testing. Factory acceptance testing will take place at Company's facilities. All Products shall be subjected to factory acceptance testing. Prior to factory acceptance testing, Company shall provide Motorola with a set of pre-FATP engineering release notes.