FACTORY TESTS Sample Clauses
The FACTORY TESTS clause establishes requirements for testing products or equipment at the manufacturer's facility before delivery to the buyer. Typically, it outlines the types of tests to be performed, the standards or procedures to be followed, and may specify the buyer's right to witness or review the results of these tests. This clause ensures that products meet agreed-upon specifications and quality standards prior to shipment, thereby reducing the risk of defects and disputes after delivery.
POPULAR SAMPLE Copied 1 times
FACTORY TESTS. Owner may, at Owner's option and cost, be -------------- present at any factory testing conducted by Vendor. Vendor shall give the Owner ten (10) Business Days advance notice of any such factory testing relating to the Products or Services furnished by Vendor hereunder. Vendor shall cooperate with Owner to facilitate Owner's observation of such tests. Regardless of whether or not Owner observes any factory testing, Vendor agrees to, within a reasonable period of time in view of the nature and urgency of the request, upon written request by Owner, provide Owner with copies of all documentation relating to factory testing of the Product specified by Owner, including without limitation copies of test procedures, test results and FCC compliance certifications.
FACTORY TESTS. The Contractor will perform all necessary testing and measurements required to demonstrate compliance with the specifications prior to delivery.
FACTORY TESTS. Contractor shall perform all customary or required factory tests of all of the Materials in accordance with the requirements set forth in Exhibit A or Exhibit R or by Owner Standards. Contractor shall issue a test memorandum to Owner no later than thirty (30) Days prior to the commencement of each factory test, which memorandum shall describe the factory test to be performed, the applicable item of Material being tested, the standards and method of testing, and the testing facility’s capabilities and shall state a proposed test date. Owner’s Representative and the representative of the Independent Engineer shall be permitted to attend and participate in all such factory tests. Contractor shall provide the results of such required factory tests to Owner within ten (10) Days of the completion of each such factory test. Successful completion of such factory test shall be a precondition to shipment of the tested item of Material.
FACTORY TESTS. .1 Submit test certificates as prescribed in the relevant section of the specifications.
FACTORY TESTS. The following standard commercial factory tests in accordance with ANSI C50.13, Table 4, Generators Not Completely Assembled in Factory for Test, will be performed on the generator: -------------------------------------------------------------------------------- Proprietary Information Page 25 AES IRONWOOD CONTRACT FINAL ISSUE - OCTOBER 30, 1998 -------------------------------------------------------------------------------- Mechanical
FACTORY TESTS. The tank fabricators shall have a quality control procedure adequate to ensure that all fabrication complies with these Specifications: 1. Impact Tests: A representative sample from each tank shall undergo a factory impact test. Impact
FACTORY TESTS. A. The following transformer tests shall be performed. The following standards shall be used for completing the test: IEEE C57.12.00, IEEE C57.12.10, IEEE C57.12.90, IEEE C57.91, IEEE C57.98, IEEE C57.109, IEEE C57.113 and IEEE C57.131.
1. Resistance measurement of all windings on the full winding tap position of each unit. Use 2,500 V test equipment and correct to 20°C temperature reference.
2. Ratio tests on the rated voltage connection and on all tap connections.
3. Polarity and phase relation tests on the rated voltage connection.
4. No-load (excitation) loss at rated frequency and at 100 percent and 110 percent of rated voltages.
FACTORY TESTS. The supplier shall detail the tests that will be applied to each power converter at the factory before shipping and should supply copies of these test results. As STFC may wish to witness some or all of the factory tests the supplier shall give a minimum of 3 weeks’ notice of the date of such tests.
FACTORY TESTS. Cricket may, at Cricket’s option and cost, request to be present at any factory testing conducted by Vendor. Upon written request, Vendor shall give Cricket twenty-one (21) Business Days advance notice of any such factory testing relating to the types of Products or Services furnished by Vendor hereunder. Vendor shall use commercially reasonable efforts to facilitate Cricket’s observation of such tests; provided such observance is permitted by Vendor’s suppliers and does not result in additional costs being charged to Vendor. Regardless of whether or not Cricket observes any factory testing, Vendor agrees to provide Cricket, upon Cricket’s specific written request, with copies of all documentation relating to factory testing of the Product specified by Cricket, including without limitation copies of test procedures, test results and FCC compliance certifications, subject to confidentiality and other limits set forth in the respective agreements between Vendor and its suppliers.
FACTORY TESTS. 1. Perform manufacturer’s standard function test on final assembly to ensure that equipment