INFORMATIONAL SUBMITTALS Sample Clauses

The 'Informational Submittals' clause requires the contractor or party performing work to provide specific documents or data to the project owner or architect for informational purposes only. These submittals might include schedules, product data, certificates, or other documentation that demonstrates compliance with project requirements but does not require formal approval. By mandating the delivery of such information, this clause ensures transparency and keeps stakeholders informed, helping to prevent misunderstandings and facilitating smooth project coordination.
INFORMATIONAL SUBMITTALS. Informational submittals upon which the Project Designer is not expected to take responsive action may be so identified in the Contract Documents.
INFORMATIONAL SUBMITTALS. Architect will review each submittal and will not return it, or will return it if it does not comply with requirements. Architect will forward each submittal to appropriate party.
INFORMATIONAL SUBMITTALS. Submittals identified in the Contract Documents are to be submitted for information only.
INFORMATIONAL SUBMITTALS. Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements. Engineer will forward each submittal to appropriate party.
INFORMATIONAL SUBMITTALS. A. Qualification Data: For the following: 1. Installer: Include copies of applicable ACI certificates. 2. Ready-mixed concrete manufacturer. 3. Testing agency: Include copies of applicable ACI certificates. B. Material Certificates: For each of the following, signed by manufacturers: 1. Cementitious materials. 2. Admixtures. 3. Curing compounds. 4. Bonding agents. 5. Adhesives.
INFORMATIONAL SUBMITTALS. A. General: Prepare and submit Informational Submittals required by other Specification Sections.
INFORMATIONAL SUBMITTALS. A. Coordination Drawings: Area plans and details, drawn to scale, on which the following items are shown and coordinated with each other, using input from installers of the items involved: 1. Structural members to which equipment will be attached. 2. Electrical service. 3. Communications service, including wireless communications equipment. B. Qualification Data: For [Installer] [factory-authorized service representative].
INFORMATIONAL SUBMITTALS. A. Qualification Data: For professional engineer and testing agency responsible for testing nonconcrete handholes and boxes.
INFORMATIONAL SUBMITTALS. A. Qualification Data: For testing and inspection agency. B. Research Reports: For insulating concrete forms indicating compliance with International Code Council Acceptance Criteria AC353. C. Field quality-control reports. D. Minutes of preinstallation conference.
INFORMATIONAL SUBMITTALS. A. Field quality-control reports.