The 'Material Test Reports' clause requires suppliers or contractors to provide documentation verifying that materials used in a project meet specified standards and quality requirements. Typically, this involves submitting certificates or reports from independent laboratories or manufacturers that detail the results of tests performed on materials such as steel, concrete, or other critical components. By mandating these reports, the clause ensures that only compliant and safe materials are incorporated into the project, thereby reducing the risk of defects and ensuring regulatory and contractual compliance.
Material Test Reports. Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
Material Test Reports. Material test results shall be verbally made available to the [Owner / Engineer] within [one hour] after the test report is completed and typed copies shall be made available within one working day [delivered via electronic mail]. • Calibration check on equipment used to determine the noncompliance item, if applicable. • Confirmation of noncompliance through retesting and/or follow-up observations. • If a solution to the nonconformance issue is not reached in a reasonable time frame, additional qualified contractor personnel will be contacted to assist in identifying and correcting the problem. • If a severe nonconformance problem is detected and a reasonable solution cannot be implemented in a reasonable time frame, the Construction Superintendent will consult with the Project Engineer and the work will be suspended. • The work will not begin again until the Construction Superintendent and Project Engineer concur that a solution to the problem has been found and successfully implemented.
Material Test Reports. For the following, from a qualified testing agency: 1. Portland cement. 2. Fly ash. 3. Slag cement. 4. Blended hydraulic cement.
Material Test Reports. Material test results shall be verbally made available to the Engineer within 3 days after the test report is completed, or when material is delivered to the site for inspection by the Engineer. Typed copies shall be made available at or prior to delivery to the site. The contractor is responsible for delivering materials that meet specification.
Material Test Reports. For existing native surface topsoil, existing in-place surface soil and imported topsoil.
Material Test Reports. From a qualified testing agency indicating and interpreting test results for compliance of the following with requirements indicated: 1. Classification according to ASTM D 2487 of each on-site and borrow soil material proposed for fill and backfill. 2. Laboratory compaction curve according to ASTM D 698 for each on-site and borrow soil material proposed for fill and backfill. 3. Compaction Density Test Reports according to ASTM D 2922 – Test Method for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth).
Material Test Reports. For the following, from a qualified testing agency:
Material Test Reports. Architect shall check and process, in a timely manner, all required material test reports for the Project work. In addition, Architect shall provide notice of any deficiencies in material or work reflected in such reports, as well as its recommendation for correction of such deficiencies, to the contractors, District and federal, state, regional or local agencies concerned with the Project, including but not limited to, the State Department of Education, the Division of State Architect, the Department of General Services or any other appropriate federal, state, regional or local regulatory bodies.

Related to Material Test Reports

  • Project Reports The Recipient shall monitor and evaluate the progress of the Project and prepare Project Reports in accordance with the provisions of Section 4.08 of the General Conditions and on the basis of the indicators agreed with the Association. Each Project Report shall cover the period of one calendar semester, and shall be furnished to the Association not later than one month after the end of the period covered by such report.

  • Cost Reports Seller, at its expense, shall, or shall cause the Seller Entities to, prepare and timely file all terminating and other cost reports required or permitted by law to be filed under the Medicare and Medicaid or other third party payor programs and the State Health Agency for periods ending on or prior to the Effective Time, or as a result of the consummation of the transactions described herein (“Seller Cost Reports”). If requested by the Seller Entities, Buyer shall include the applicable Seller Entity’s Medicare bad debts that are returned from collection agencies subsequent to the Closing Date on Buyer’s cost report for the respective period to which the Medicare bad debt relates. The Seller Entity shall provide detailed supporting information, as required by Medicare regulations, for the Medicare bad debt account amounts to be included on Buyer’s Medicare cost report. Buyer shall forward to Seller any and all correspondence relating to the Seller Cost Reports within five (5) business days after receipt by ▇▇▇▇▇. Buyer shall remit any receipts of funds relating to the Seller Cost Reports promptly after receipt by ▇▇▇▇▇ and shall forward to Seller any demand for payments within three (3) business days after receipt by ▇▇▇▇▇. Notwithstanding anything to the contrary in this Agreement, Seller shall retain all rights to the Seller Cost Reports including any amounts receivable or payable in respect of such reports or reserves relating to such reports and all liabilities relating thereto. Such rights shall include the right to appeal any Medicare or Medicaid determinations relating to the Seller Cost Reports. Seller shall retain the originals of the Seller Cost Reports, correspondence, work papers and other documents relating to the Seller Cost Reports. Seller will furnish copies of such cost reports to Buyer upon request.

  • Material Safety Data Sheet The contractor shall provide Material Safety Data Sheets (MSDS) with the information required by the Act and the regulations for each hazardous substance or hazardous mixture. The Commonwealth must be provided an appropriate MSDS with the initial shipment and with the first shipment after an MSDS is updated or product changed. For any other chemical, the contractor shall provide an appropriate MSDS, if the manufacturer, importer, or supplier produces or possesses the MSDS. The contractor shall also notify the Commonwealth when a substance or mixture is subject to the provisions of the Act. Material Safety Data Sheets may be attached to the carton, container, or package mailed to the Commonwealth at the time of shipment.

  • Adverse Event Reporting Both Parties acknowledge the obligation to comply with the Protocol and / or applicable regulations governing the collection and reporting of adverse events of which they may become aware during the course of the Clinical Trial. Both Parties agree to fulfil and ensure that their Agents fulfil regulatory requirements with respect to the reporting of adverse events.

  • Status Reports The Grantee shall submit status reports quarterly, unless otherwise specified in the Attachments, on Exhibit A, Progress Report Form, to Department’s Grant Manager describing the work performed during the reporting period, problems encountered, problem resolutions, scheduled updates, and proposed work for the next reporting period. Quarterly status reports are due no later than twenty (20) days following the completion of the quarterly reporting period. For the purposes of this reporting requirement, the quarterly reporting periods end on March 31, June 30, September 30 and December 31. The Department will review the required reports submitted by Grantee within thirty (30) days.