False Start. In the event the CMR shall have issued notice of readiness prematurely, his action shall be deemed to be a "false start.” The CMR shall be liable for the damage resulting from the aforesaid false start, including, but not limited to, the salary, professional fees, and travel and living expenses of the person or parties inconvenienced by the aforesaid false start.