Final Completion Date. The date established in the Agreement by which the Design-Builder shall achieve Final Completion. The Final Completion Date may be modified only by Change Order or Change Directive in accordance with the Agreement.
Appears in 24 contracts
Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement
Final Completion Date. The date established in the Agreement herein by which the Design-Builder Contractor shall achieve Final Completion. The Final Completion Date may be modified only by Change Order or Change Directive in accordance with the Agreement.
Appears in 10 contracts
Sources: Construction Agreement, Construction Agreement, Construction Agreement
Final Completion Date. The date established in the Agreement Contract by which the Design-Builder Contractor shall achieve Final Completion. The Final Completion Date may be modified only by Change Order “Change Order”) or Change Directive in accordance with the Agreement.
Appears in 5 contracts
Sources: Construction Management Agreement, Construction Management Agreement, Construction Management at Risk Services Agreement
Final Completion Date. The date established in the Agreement by which the Design-Builder Construction Manager shall achieve Final Completion. The Final Completion Date may be modified only by Change Order or Change Directive in accordance with the Agreement.
Appears in 2 contracts
Sources: Construction Management at Risk Agreement, Construction Management at Risk Agreement
Final Completion Date. The date established in the Agreement Contract by which the Design-Builder Construction Manager shall achieve Final Completion. The Final Completion Date may be modified only by Change Order or Change Directive in accordance with the Agreement.
Appears in 2 contracts
Sources: Construction Management at Risk Agreement, Construction Management at Risk Agreement