Final Completion Sample Clauses

The Final Completion clause defines the point at which all contractual work is fully finished and accepted by the owner or client. In practice, this clause typically requires the contractor to complete all outstanding items, resolve any deficiencies, and submit necessary documentation such as warranties or as-built drawings before final approval is granted. Its core function is to establish a clear endpoint for the contractor’s obligations, ensuring that all aspects of the project are satisfactorily completed before final payment is released.
POPULAR SAMPLE Copied 9 times
Final Completion. The full and final completion of all Work in accordance with the Contract Documents.
Final Completion. Final Completion shall be evidenced by the Design Professional’s Certificate of Final Completion. Final Completion should include completion of Permitted Incomplete Work, as defined in Section 6, Part 1.
Final Completion. The point at which Substantial Completion has been achieved, all punch list items noted at Substantial Completion have been completed and all documents the Design-Builder is required to deliver to the Department as a condition to receiving final payment have been delivered.
Final Completion. Construction Manager shall pay Owner Five Hundred Dollars ($500.00) as liquidated damages for each day that Final Completion extends beyond the Final Completion Date.
Final Completion. Monitor the Sub-Contractor’s performance on the completion of the project and provide notice to the Owner and Architect-Engineer that the work is ready for final inspection. Secure and transmit to the Owner, through the Architect-Engineer, all required guarantees, affidavits, releases, bonds and waivers, manuals, record drawings, and maintenance books including the Contract Completion form shown in Exhibit G.
Final Completion. Full completion of all Work required by the Contract Documents, including all punch list items, and submission of Record Documents, all to City’s satisfaction.
Final Completion. Monitor the subcontractors’ performance on the completion of the Work and provide notice to Owner and Design Professional when the Work is ready for final inspection. Secure, review and certify compliance with the Contract Documents, then transmit to Owner, through Design Professional, and as an express condition precedent to final payment, all required guarantees, warranties, affidavits, releases, consent of surety to final payment, bonds, waivers, manuals, as-built drawings, and maintenance books.
Final Completion. Subject to the occurrence of the FNTP Date, Seller shall cause the Work to achieve Final Completion. If and when ▇▇▇▇▇▇ considers that the Work has achieved Final Completion, Seller shall certify the same to Buyer in writing by delivering a certificate substantially in the form of Exhibit BB (the “Final Completion Certificate”) signed by a duly authorized representative of Seller. Buyer shall, within fifteen (15) Business Days after receipt of such Final Completion Certificate, either (a) confirm in writing to Seller that it agrees that the Work has achieved Final Completion or (b) notify Seller in writing that it does not agree that the Work has achieved Final Completion and provide in reasonable detail an explanation of the basis for its disagreement. If Buyer provides Seller with a notice pursuant to clause (b) immediately above, Seller shall address and resolve any and all deficiencies in the Work and resubmit its Final Completion Certificate to Buyer. For the purposes of this Agreement, the Work shall be deemed to have achieved Final Completion on the earlier of (i) the date Buyer confirms in writing to Seller that it agrees the Work has achieved Final Completion and (ii) if within fifteen (15) Business Days after receipt from Seller of the Final Completion Certificate, ▇▇▇▇▇ has neither confirmed in writing that it agrees the Work has achieved Final Completion nor provided Seller a notice pursuant to clause (b) above, the fifteenth (15th) Business Day after Seller issues Buyer a written certification that the Work has achieved Final Completion Certificate in accordance with the requirements of this Agreement.
Final Completion. The Work shall be fully and finally completed on or before TBD; provided, however, Owner may extend said time period in the event bad weather affects the progress of the Work. Owner shall, at its sole discretion, determine when the Work has been fully and finally completed to its satisfaction.
Final Completion. In order to achieve Final Completion, Northwind must have: (i) achieved Substantial Completion, (ii) corrected all conditions constituting Defects and Deficiencies identified in writing by Aladdin to Northwind, (iii) performed all other obligations of Northwind under this Agreement to be then performed, in a manner reasonably satisfactory to Aladdin, and (iv) delivered to Aladdin a certificate of final completion (the "Final Completion Certificate"), which shall be in the form agreed to by the Parties, initialed by the Parties and attached hereto as Exhibit F by not later than thirty (30) days after Notice to Proceed is received by Northwind. If Aladdin believes, at the time of such certification by Northwind, that the Plant has not reached Final Completion, then within ten (10) Business Days of Aladdin's receipt of the Final Completion Certificate, Aladdin shall provide Northwind with written notice clearly setting forth the basis for Aladdin's belief. Any portions of the Plant to which timely objection is not made by Aladdin shall be considered to have reached Final Completion. Failure by Aladdin to deliver any notice within such ten (10) Business Day period shall be deemed acknowledgment by Aladdin that Final Completion has occurred. If Aladdin delivers a notice to Northwind as aforesaid, Northwind shall determine whether it agrees with Aladdin's notice. If Northwind agrees with Aladdin's notice, Northwind shall take the actions necessary to bring the Plant to Final Completion. In the event Northwind contests Aladdin's notification that Final Completion has not been achieved, Aladdin and Northwind shall promptly confer and exert their best efforts in good faith to reach a reasonable and equitable resolution of the issue. If Aladdin and Northwind are unable to resolve the issue within five (5) Business Days, the matter shall be referred to the Independent Engineer. The Parties agree to accept the determination made by the Independent Engineer with respect to whether Final Completion has been achieved and to act accordingly.