Final Completion. Construction Manager shall pay Owner Five Hundred Dollars ($500.00) as liquidated damages for each day that Final Completion extends beyond the Final Completion Date.
Appears in 115 contracts
Sources: Agreement for Construction Management Services, Guaranteed Maximum Price Agreement, Construction Management Services Agreement
Final Completion. Construction Manager shall pay Owner Five Two Hundred Fifty Dollars ($500.00250.00) as liquidated damages for each day that Final Completion extends beyond the Final Completion Date.
Appears in 9 contracts
Sources: Guaranteed Maximum Price Agreement, Guaranteed Maximum Price Agreement, Guaranteed Maximum Price Agreement
Final Completion. Construction Manager shall pay Owner Five Hundred Dollars ($500.00250.00) as liquidated damages for each day that Final Completion extends beyond the Final Completion Date.
Appears in 2 contracts
Sources: Guaranteed Maximum Price Agreement, Guaranteed Maximum Price Agreement
Final Completion. Construction Manager shall pay Owner Five Hundred Dollars ($500.00) as liquidated damages for each day that Final Completion extends beyond the Final Completion DateDate for each phase of the project.
Appears in 2 contracts
Sources: Guaranteed Maximum Price Agreement, Construction Management Services Agreement
Final Completion. Construction Manager shall pay Owner Five Two-Hundred Fifty Dollars ($500.00250.00) as liquidated damages for each day that Final Completion extends beyond the Final Completion Date.
Appears in 1 contract
Sources: Guaranteed Maximum Price Agreement
Final Completion. Construction Manager shall Managershall pay Owner Five Hundred Dollars ($500.00) as liquidated damages for each day that Final Completion extends beyond the Final Completion Date.
Appears in 1 contract