Common use of For Force Majeure Clause in Contracts

For Force Majeure. Either party may terminate this agreement on 10 Working Days’ notice, if a Force Majeure Event hinders one or both of the parties in the performance of their obligations under this agreement to an extent, and for a duration, which makes it unreasonable or impracticable for the terminating party to be required to continue with this agreement. A party may only terminate under this clause 17.3 if it has complied in all material respects with its obligations under clause 16 in relation to the relevant Force Majeure Event.