GMP Plans and Specifications. The Owner shall authorize and cause the Engineer of Record to review the Plans and Specifications to the extent necessary to reflect the agreed-upon assumptions and clarifications contained in the GMP Amendment. Such revised Plans and Specifications shall be furnished to the CM/GC in accordance with schedules agreed to by the Owner, Engineer of Record and CM/GC. The CM/GC shall promptly notify the Engineer of Record and the Owner if such revised Plans and Specifications are inconsistent with the agreed-upon assumptions and clarifications. Additionally, the CM/GC shall work with the Engineer of Record and the Owner to identify and confirm any Work not specifically shown but required for a complete, fully functional project.