Common use of GMP Plans and Specifications Clause in Contracts

GMP Plans and Specifications. The Owner shall authorize and cause the Engineer of Record to review the Plans and Specifications to the extent necessary to reflect the agreed-upon assumptions and clarifications contained in the GMP Amendment. Such revised Plans and Specifications shall be furnished to the CM/GC in accordance with schedules agreed to by the Owner, Engineer of Record and CM/GC. The CM/GC shall promptly notify the Engineer of Record and the Owner if such revised Plans and Specifications are inconsistent with the agreed-upon assumptions and clarifications. Additionally, the CM/GC shall work with the Engineer of Record and the Owner to identify and confirm any Work not specifically shown but required for a complete, fully functional project.

Appears in 3 contracts

Sources: Cm/Gc Contract, Construction Manager/General Contractor Contract, Cm/Gc Contract