Grounds for Extension Sample Clauses

The "Grounds for Extension" clause defines the specific circumstances under which a party may request additional time to fulfill contractual obligations. Typically, this clause outlines valid reasons such as unforeseen delays, force majeure events, or changes in project scope that justify extending deadlines. By clearly specifying what qualifies as acceptable grounds for an extension, the clause helps prevent disputes over schedule changes and ensures both parties have a mutual understanding of when and how extensions can be granted.
POPULAR SAMPLE Copied 1 times
Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely: 13.3.1 By the acts or omissions of the City, its officials, agents or employees; or 13.3.2 By the act or omissions of Other Contractors on this Project; or 13.3.3 By supervening conditions entirely beyond the control of either party hereto (such as, but not limited to, acts of God or the public enemy, excessive inclement weather, war or other national emergency making performance temporarily impossible or illegal, or strikes or labor disputes not brought about by any act or omission of the Contractor). 13.3.4 The Contractor shall, however, be entitled to an extension of time for such causes only for the number of Days of delay which the ACCO or the Board may determine to be due solely to such causes, and then only if the Contractor shall have strictly complied with all of the requirements of Articles 9 and 10.
Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely: 41.3.1. By the acts or omissions of the City, its officials, agents or employees; or 41.3.2. By the act or omissions of Other Contractors on this Project; or 41.3.3. By supervening conditions entirely beyond the control of either party hereto (such as, but not limited to, acts of God or the public enemy, excessive inclement weather, war or other national emergency making performance temporarily impossible or illegal, or strikes or labor disputes not brought about by any act or omission of the Contractor).
Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely:
Grounds for Extension. The Contractor shall be granted an extension of time for delay caused solely: 3.1 By the acts or omissions of the City, its officers, agents, or employees; 13A. 3.2 By the act or omissions of other Contractors on a project; or 3.3 By supervening conditions entirely beyond the control of either party hereto (such as, but not limited to, Acts of God or the public enemy, excessive inclement weather, war or other national emergency making performance temporarily impossible or illegal, or strikes or labor disputes not brought about by any act or omission of the Contractor).
Grounds for Extension. If such written application is made to the Director, the Construction Manager shall be entitled to an extension of time for delay in completion of Work, if such delay is caused solely: (1) by the acts or omissions of CUCF, its officers, agents or employees; or (2) by the act or omissions of other contractors; or (3) by unavoidable delay, as defined in Article 1.35 hereof, or other supervening conditions entirely beyond the control of either party hereto. The Construction Manager shall, however, be entitled to an extension of time for such causes only for the number of days of delay which the Director may determine to be due solely to such causes, and then only if the Construction Manager shall have strictly complied with all of the requirements of Articles 8, 16, and 17 hereof.
Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely: 47.3.1. By the acts or omissions of the City, its officers, agents or employees; or 47.3.2. By the act or omissions of Other Contractors on this Project; or 47.3.3. By supervening conditions entirely beyond the control of either party hereto (such as, but not limited to, acts of God or the public enemy, excessive inclement weather, war or other national emergency making performance temporarily impossible or illegal, or strikes or labor disputes not brought about by any act or omission of the Contractor). 47.3.4. The Contractor shall, however, be entitled to an extension of time for such causes only for the number of Days of delay which the Commissioner or the Board may determine to be due solely to such causes, and then only if the Contractor shall have strictly complied with all of the requirements of the Contract.
Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely: 13.3.1 By any of the acts or omissions of the City, its officials, agents or employees set forth in Articles 11.4.1.1 through 11.4.1.9; or 13.3.2 By or attributable to any of the items set forth in Articles 11.5.1 through 13.3.3 The Contractor shall, however, be entitled to an extension of time for such causes only for the number of Days of delay which the ACCO or the Board may determine to be due solely to such causes, and then only if the Contractor shall have strictly complied with all of the requirements of Articles 9 and 10
Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of subcontracted work, if such delay is caused solely: (1) by the acts or omissions of the City, its officers, agents or employees; or (2) by the act or omissions of other contractors or a Homeowner; or (3) by Unavoidable Delay, as defined in Article 1.35 hereof, or other supervening conditions entirely beyond the control of either party hereto. The Contractor shall, however, be entitled to an extension of time for such causes only for the number of days of delay which the Commissioner may determine to be due solely to such causes, and then only if the Contractor shall have strictly complied with all of the requirements of Articles 8, 16, and 17 hereof.

Related to Grounds for Extension

  • Grounds for exclusion Purely national exclusion grounds: 5 Lot 5.1 Lot technical ID: LOT-0001

  • Credit for Experience 33.01 Credit for nursing experience will be credited on the following basis: (a) The Employer will credit a newly hired regular full-time nurse with one (1) annual service increment for each completed year of related experience up to the after eight (8) years step of the salary grid and credit a regular part-time nurse, up to the after twelve thousand (12,000) hours step, based on substantiated hours worked. (b) If there has been a break in excess of two years in the nurses’ full-time or part-time employment, then the number of increments to be provided shall be at the discretion of the Employer. 33.02 In order to receive credit for experience it is the nurse’s responsibility to provide the Employer with verification satisfactory to the Employer, of previous related experience during her probationary period. Should a nurse fail to provide such satisfactory verification during her probation she shall forfeit the provisions of this Article. 33.03 Once established consistent with the above provisions, credit for recent related experience will be retroactive to the new nurses date of hire. 33.04 Nurses on staff prior to the signing of this agreement, will be credited with experience as set out under this Article, effective the first full pay period following the date the Employer has confirmed entitlement to such increment, subject to 33.02 above.