Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost $150,000 equivalent or more each.
Appears in 1 contract
Sources: Development Credit Agreement
Grouping of contracts. To the extent practicable, contracts for works estimated to cost $300,000 equivalent or more each and, contracts for goods estimated to cost $100,000 equivalent or more each shall be grouped in bid packages estimated to cost $150,000 equivalent or more eachpackages.
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost the equivalent of $150,000 10,000,000 or more each, and contracts for goods shall be grouped into bid packages estimated to cost the equivalent of $200,000 or more each.
Appears in 1 contract
Sources: Project Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost $150,000 2,000,000 equivalent or more each.
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for goods and works shall be grouped in bid packages estimated to cost $150,000 1,000,000 equivalent or more each.
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for goods shall be grouped in bid packages estimated to cost $500,000 equivalent or more each, and contracts for works shall be grouped in bid packages estimated to cost $150,000 2,000,000 equivalent or more each.
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for works goods and work shall be grouped in bid packages estimated to cost $ 200,000 and $150,000 50,000 equivalent or more eacheach respectively.
Appears in 1 contract
Sources: Development Credit Agreement
Grouping of contracts. To the extent practicable, contracts for goods and works shall be grouped in into bid packages estimated to cost the equivalent of, respectively, $150,000 350,000 equivalent and $5,000,000 equivalent or more each.
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for goods shall be grouped in bid packages estimated to cost €200,000 equivalent or more each and contracts for works shall be grouped in bid packages estimated to cost $150,000 €1,000,000 equivalent or more each.
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost $150,000 2,000,000 equivalent or more each.
Appears in 1 contract
Sources: Development Credit Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost $150,000 300,000 equivalent or more each, and contracts for goods shall be grouped in bid packages estimated to cost $100,000 equivalent or more each.
Appears in 1 contract
Sources: Development Credit Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost the equivalent of nineteen million dollars ($150,000 equivalent 19,000,000) or more each.
Appears in 1 contract
Sources: Development Credit Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost $150,000 10,000,000 equivalent or more each, and contracts for goods shall be grouped in bid packages estimated to cost $1,000,000 equivalent or more each.
Appears in 1 contract
Sources: Shanxi Project Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost the equivalent of $150,000 equivalent 600,000 or more eachmore.
Appears in 1 contract
Sources: Development Credit Agreement
Grouping of contracts. To the extent practicable, contracts for goods and works shall be grouped in bid packages estimated to cost $150,000 and $500,000, equivalent or more each, respectively.
Appears in 1 contract
Sources: Development Grant Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost the equivalent of $150,000 10,000,000 or more each, and contracts for goods shall be grouped into bid packages estimated to cost the equivalent of $250,000 or more each.
Appears in 1 contract
Sources: Project Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost $150,000 600,000 equivalent or more each.
Appears in 1 contract
Sources: Development Credit Agreement
Grouping of contracts. To the extent practicable, contracts for works and goods shall be grouped in bid packages estimated to cost cost, respectively, $150,000 500,000 and $100,000 equivalent or more each.
Appears in 1 contract
Sources: Project Agreement
Grouping of contracts. To the extent practicable, contracts for goods and works shall be grouped in bid packages estimated to cost cost, respectively, more than the equivalent of $150,000 equivalent or more 250,000 and $4,000,000 each.
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for goods and works shall be grouped in bid packages estimated to cost $150,000 250,000 equivalent or more each and $3,000,000 equivalent or more each, respectively.
Appears in 1 contract
Sources: Project Agreement
Grouping of contracts. To the extent practicable, : (i) contracts for works goods shall be grouped in bid packages estimated to cost $150,000 equivalent or more each; and (ii) contracts for works shall be grouped in bid packages estimated to cost $1,000,000 equivalent or more each.
Appears in 1 contract
Sources: Development Grant Agreement
Grouping of contracts. To the extent practicable, contracts for goods and works shall be grouped in into bid packages estimated to cost $150,000 the equivalent of DEM 1,500,000 or more each.. Part C: Other Procurement Procedures
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for goods shall be grouped in bid packages estimated to cost €300,000 equivalent or more each, and contracts for works shall be grouped in bid packages estimated to cost $150,000 equivalent €3,000,000 or more each.
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for goods shall be grouped in bid packages estimated to cost $400,000 equivalent or more each, and contracts for works shall be grouped in bid packages estimated to cost $150,000 2,000,000 equivalent or more each.
Appears in 1 contract
Sources: Development Financing Agreement
Grouping of contracts. To the extent practicable, (i) contracts for works shall be grouped in bid packages estimated to cost $150,000 7,000,000 equivalent or more each; and (ii) contracts for goods shall be grouped in bid packages estimated to cost $500,000 equivalent or more each.
Appears in 1 contract
Sources: Project Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in by bid packages estimated to cost $150,000 200,000 equivalent or more each and for goods of $100,000 equivalent or more each.. Part C: Other Procurement Procedures
Appears in 1 contract
Sources: Trust Fund Grant Agreement
Grouping of contracts. To the extent practicable, contracts for goods and works shall be grouped in bid packages estimated to cost respectively $150,000 200,000 and $1,500,000 equivalent or more each.
Appears in 1 contract
Sources: Loan Agreement
Grouping of contracts. To the extent practicable, contracts for works shall be grouped in bid packages estimated to cost $150,000 2,000,000 equivalent or more each and contracts for goods shall be grouped in bid packages estimated to cost $250,000 equivalent or more each.
Appears in 1 contract
Sources: Development Credit Agreement
Grouping of contracts. To the extent practicable, practicable contracts for goods and related installation works shall be grouped in bid packages estimated to cost five million dollars ($150,000 5,000,000) equivalent or more each.
Appears in 1 contract
Sources: Loan Agreement