Implementation Phase. 1. Final Project Work Plan shall be delivered to DCH no later than 15 calendar days after contract signing. Within a week, DCH will indicate if plan is acceptable or not and if necessary when changes must be submitted. 2. Data Conversion and Downloading shall be complete by September 1, 2005. 3. Required staffing levels shall be in place by September 1, 2005 and remain in place throughout the life of the contract. 4. Data enhancements/corrections shall be complete or identified in a corrective action plan by November 1, 2005. 5. Data Warehouse data transfer shall be complete by December 1, 2005. 6. EIS Reports shall be completely designed by December 1, 2005. 7. Training materials, equipment, and documents shall be submitted for approval by December 1, 2005. 8. Operational Readiness Testing shall be complete by December 16, 2005. 9. Installation of the base system and all necessary equipment shall be complete by January 3, 2006. 10. All actions set forth in the corrective action plan shall be complete by January 3, 2006. 11. Implementation Phase shall be complete by January 3, 2006. 12. Final user training for all products shall be complete by March 1, 2006.
Appears in 1 contract
Implementation Phase. 1. Final Project Work Plan shall be delivered to DCH no later than 15 calendar days after contract signing. Within a week, DCH will indicate if plan is acceptable or not and if necessary when changes must be submitted.will
2. Data Conversion and Downloading shall be complete by September 1, 2005.2005.
3. Required staffing levels shall be in place by September 1, 2005 and remain in place throughout the life of the contract.
4. Data enhancements/corrections shall be complete or identified in a corrective action plan by November 1, 2005.2005.
5. Data Warehouse data transfer shall be complete by December 1, 2005.
6. EIS Reports shall be completely designed by December 1, 2005.
7. Training materials, equipment, and documents shall be submitted for approval by December 1, 2005.2005.
8. Operational Readiness Testing shall be complete by December 16, 2005.
9. Installation of the base system and all necessary equipment shall be complete by January 3, 2006.
10. All actions set forth in the corrective action plan shall be complete by January 3, 2006.2006.
11. Implementation Phase shall be complete by January 3, 2006.
12. Final user training for all products shall be complete by March 1, 2006.
Appears in 1 contract