Installed Capacity Clause Samples
The Installed Capacity clause defines the maximum output or production capability of a facility, equipment, or system as agreed upon in a contract. It typically specifies the rated capacity, such as megawatts for a power plant or units per hour for manufacturing equipment, and may outline how this capacity is measured or verified. This clause ensures both parties have a clear understanding of the performance expectations and helps prevent disputes over whether the delivered system meets contractual requirements.
Installed Capacity. A Generator, Distributed Generator, Demand Response Provider, or Load facility that complies with the requirements in the Reliability Rules and is capable of supplying and/or reducing the demand for Energy in the NYCA for the purpose of ensuring that sufficient Energy and Capacity are available to meet the Reliability Rules. The Installed Capacity requirement, established by the NYSRC, includes a margin of reserve in accordance with the Reliability Rules. Interconnection or Interconnection Points (“IP”). The point(s) at which the NYCA connects with a distribution system or adjacent Control Area. The IP may be a single tie line or several tie lines that are operated in parallel.
Installed Capacity. 3.1.1 The SPD shall configure the project with the objective of supplying solar power to the Buying Entity. Accordingly, the Project Capacity, i.e. the Installed Capacity shall mean the rated capacities of the Solar Power Project and ESS components, in the following configuration: Solar: ▇▇ ▇▇▇: MW/ MWh
3.1.2 The above configuration shall be identical to the “installed capacity” for which connectivity has been granted to the SPD under the GNA Regulations. Also, any change in Delivery Point is allowed up to the deadline for Financial Closure as per Article 3.4
Installed Capacity. A Generator or Load facility that complies with the requirements in the Reliability Rules and is capable of supplying and/or reducing the demand for Energy in the NYCA for the purpose of ensuring that sufficient Energy and Capacity are available to meet the Reliability Rules. The Installed Capacity requirement, established by the NYSRC, includes a margin of reserve in accordance with the Reliability Rules.
Installed Capacity. 3.1.1 The RPD shall configure the Project components with the objective of supplying Firm and Dispatchable RE power to the Buying Entity. Accordingly, the Project Capacity,
Installed Capacity. 3.1.1 The WPD shall configure the project with the objective of supplying wind power to the Buying Entity. Accordingly, the Project Capacity, i.e. the Installed Capacity shall mean the rated capacity of the Wind Power Project.
3.1.2 The above configuration shall be identical to the “installed capacity for which connectivity has been granted to the WPD under the GNA Regulations. Also, any change in Delivery Point is allowed up to the deadline for Financial Closure as per Article 3.4
Installed Capacity i. in case of coal, lignite, gas engines and hydro stations, means the summation of the name plate capacities of all the units of the generating station or Maximum Continuous Rating of the generating station; and
ii. in case of solar/ wind generating stations and generating stations using inverters, means the summation of the name plate capacities of wind turbines or solar generating units in terms of AC capacity in KW; and
iii. in case of biomass, Municipal solid waste plant and bagasse generating stations, means the summation of the name plate capacities of the generating unit, as the case may be.
Installed Capacity. Niagara Mohawk shall retain the right to claim the Capacity, and Producer must provide such Capacity, for Niagara Mohawk's capacity requirements to the NYPP or the NYISO up to the Maximum Capacity set forth in Schedule A. In the event the Producer is unable to provide Capacity acceptable to the NYPP or NYISO in the amount claimed by Niagara Mohawk from its (Producer's) own sources, the Producer must procure the Capacity from the market and provide it to Niagara Mohawk at no cost to Niagara Mohawk. In the event the Producer fails to provide such Capacity, Producer shall be charged a penalty equivalent to the greater of (i) the penalty rate assessed by the NYPP or NYISO, or (ii) the capacity rate component of Niagara Mohawk's Service Classification Number 6 Tariff.
Installed Capacity. 3.1.1 The HPD shall configure the project with the objective of supplying power to the Buying Entity. Accordingly, the Project Capacity i.e. the Installed Capacity shall mean the rated power capacity of each component, which shall be at least 33% of the Contracted Capacity. The rated capacities of the various components are as follows: Solar PV component: MW Wind Power component: MW (to be filled as per project configuration).
3.1.2 The above configuration shall be identified to the “installed capacity” for which connectivity has been granted to the HPD under the GNA regulations. Also, any change in Delivery Point is allowed upto the date as on 12 months after the Effective Date. The above change in Delivery Point shall be allowed by SECI only in case the scheduled commissioning date of the ISTS-substation of the proposed revised Delivery Point is on or before the scheduled commissioning date of the existing Delivery Point of the Project, at the time of seeking approval of such change in Delivery Points by the HPD from SECI.
Installed Capacity. 3.3.1 The SPD shall configure the Project with the objective of supplying solar power to the Buying Entity. Accordingly, the Project Capacity, i.e. the Installed Capacity shall mean the rated capacity of the Solar Power Project.
3.3.2 The above configuration shall be identified as the “installed capacity” for which connectivity has been granted to the SPPD/SPD under the UPERC Regulations. Also, any change in Delivery Point is allowed up to the date as on twelve (12) Months after the Effective Date. The above change in Delivery Point shall be allowed by UPPCL only in case the scheduled commissioning date of the Grid Substation of the proposed revised Delivery Point is on or before the scheduled commissioning date of the existing Delivery Point of the Project, at the time of seeking approval of such change in Delivery Points by the SPD from UPPCL.
Installed Capacity. 3.1.1 The WPD shall configure the project with the objective of supplying wind power to the Buying Entity. Accordingly, the Project Capacity, i.e. the Installed Capacity shall mean the rated capacity of the Wind Power Project.
3.1.2 The above configuration shall be identified to the “installed capacity for which connectivity has been granted to the WPD under the GNA regulations. Also, any change in Delivery Point is allowed upto the date as on 12 months after the Effective Date. The above change in Delivery Point shall be allowed by SECI only in case the scheduled commissioning date of the ISTS-substation of the proposed revised Delivery Point is on or before the scheduled commissioning date of the existing Delivery Point of the Project, at the time of seeking approval of such change in Delivery Points by the WPD from SECI.