Interconnection with Electric Distribution Grid Clause Samples

The "Interconnection with Electric Distribution Grid" clause defines the terms and conditions under which a facility or project connects to the local electric distribution network. It typically outlines the technical requirements, responsibilities for upgrades or modifications, and procedures for obtaining necessary approvals from the utility. This clause ensures that the interconnection process is safe, reliable, and compliant with regulatory standards, thereby preventing disputes and operational issues related to grid access.
Interconnection with Electric Distribution Grid. Lessee will obtain at its sole cost all approvals and agreements required for Lessee’s interconnection of the System to the LDC System. Lessee will promptly inform Lessor of all significant developments relating to such interconnection matters.
Interconnection with Electric Distribution Grid. Owner will obtain at its sole cost all approvals and agreements required for Owner’s interconnection of the System to the LDC System. Owner will promptly inform User of all significant developments relating to such interconnection matters.
Interconnection with Electric Distribution Grid. Cooperative shall obtain at its sole cost all Permits and agreements required for Cooperative’s interconnection of the PV System to the electric distribution grid maintained by the Distribution Company. Cooperative shall promptly inform Host Town of all significant developments relating to such interconnection matters. Host Town shall provide Cooperative with such information as Cooperative may reasonably request in connection with Cooperative’s procurement of such Permits and agreements. If any material changes in plans and/or specifications to the PV System are required by the applicable electric distribution company, then Cooperative shall submit such changes, if any, to Host Town for its approval, which shall not be unreasonably withheld.
Interconnection with Electric Distribution Grid. Developer shall obtain at its sole cost all Permits and agreements required for Developer’s interconnection of the PV System to the electric distribution grid maintained by the Distribution Company. Developer shall promptly inform Host and CVEC of all significant developments relating to such interconnection matters. Host shall provide Developer with such information as Developer may reasonably request in connection with Developer’s procurement of such Permits and agreements. If any material changes in plans and/or specifications to the PV System are required by the applicable electric distribution company, then Developer shall submit such changes, if any, to Host and CVEC for their approval, which shall not be unreasonably withheld.
Interconnection with Electric Distribution Grid. Contractor will obtain at its sole cost all approvals and agreements required for Contractor’s interconnection of the System to the LDC System. Contractor will promptly inform County of all significant developments relating to such interconnection matters.
Interconnection with Electric Distribution Grid. (a) Contractor shall secure interconnection approval from the LDC and complete all required tasks to interconnect each System to the LDC System at no cost to Customer, except as stated in Section 4.14(b), including filing interconnection applications and paying application and impact study fees (if required). (b) The Electricity Rate includes LDC construction charges of up to the amount shown in Attachment 5: Cost and Generation, for each System. If a System’s actual interconnection charges exceed the amounts shown on Attachment 5, Customer shall pay the excess amount either, in its discretion, through a Price Adjustment of the Electricity Rate, or by a direct payment to the LDC, as follows:  Price Adjustment of the Electricity Rate: Contractor shall add a surcharge to the monthly invoice at the rate shown on Attachment 5: Cost and Generation. If the proposed Price Adjustment is greater than $0.01/kWh for any System, Customer may terminate the Contract with respect only to that System.  Direct Pay to LDC: Subject to Massport approval, Customer shall directly and timely pay the LDC so as to avoid construction delays. If the proposed payment is greater than the amount stated on the relevant Attachment 5 for that System, Customer may terminate the Contract with respect only to that System. A System’s Project Schedule (Attachment 7) shall be extended without cost to Contractor by the amount of any delay caused by Customer’s failure to timely pay this amount. (c) Contractor will promptly inform Customer of all significant developments relating to interconnection matters.
Interconnection with Electric Distribution Grid. Developer will obtain at its sole cost all approvals and agreements required for Developer’s interconnection of the System to the LDC System. Developer will promptly inform Town of all significant developments relating to such interconnection matters.

Related to Interconnection with Electric Distribution Grid

  • Network Interconnection Methods 3.1 The Interconnection provided herein may not be used solely for the purpose of originating a Party’s own interexchange traffic.

  • Interconnection Facilities 4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The NYISO, in consultation with the Connecting Transmission Owner, shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, the NYISO, and the Connecting Transmission Owner. 4.1.2 The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities, and

  • Purpose of Interconnection Facilities Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Generating Facility to the Participating TO’s Transmission System and shall be used for no other purpose.

  • Interconnection 2.1 This section applies to linking with suppliers providing public telecommunications transport networks or services in order to allow the users of one supplier to communicate with users of another supplier and to access services provided by another supplier, where specific commitments are undertaken.

  • COSTS DISTRIBUTED THROUGH COUNTYWIDE COST ALLOCATIONS The indirect overhead and support service costs listed in the Summary Schedule (attached) are formally approved as actual costs for fiscal year 2022-23, and as estimated costs for fiscal year 2024-25 on a “fixed with carry-forward” basis. These costs may be included as part of the county departments’ costs indicated effective July 1, 2024, for further allocation to federal grants and contracts performed by the respective county departments.