Interim Completion Dates. The Proposer’s initial Baseline Schedule shall establish the completion dates for each individual bridge in the Contract. Those completion dates shall be considered Interim Completion Dates and shall become the Contractual completion dates for those bridges. The interim Completion Dates may not be changed without written approval by the