Introduction of a Change. 12.1.1 For all changes to this Contract, whether requested by the Local Administrator or initiated by the Contractor, the Contractor shall submit a proposal for a Contract Change Notice (“CCN”). 12.1.2 The Contractor shall ensure - in liaison with the Local Administrator - that each CCN proposal is fully coordinated and that all reasonably foreseeable implications of the change have been considered by the Contractor and the Local Administrator. The Contractor shall, on the request of the Local Administrator provide additional documentary evidence of the effect of the change to both Parties.
Appears in 2 contracts
Sources: Esa Spark Funding Contract, Esa Spark Funding Contract
Introduction of a Change. 12.1.1 11.1.1 For all changes to this Contract, whether requested by the Local Administrator Centre or initiated by the ContractorApplicant, the Contractor Applicant shall submit a proposal for a Contract Change Notice (“CCN”).
12.1.2 11.1.2 The Contractor Applicant shall ensure - in liaison with the Local Administrator Centre - that each CCN proposal is fully coordinated and that all reasonably foreseeable implications of the change have been considered by the Contractor Applicant and the Local AdministratorCentre. The Contractor Applicant shall, on the request of the Local Administrator Centre, provide additional documentary evidence of the effect of the change to both Parties.
Appears in 1 contract
Sources: Esa Spark Funding Contract