The Lien Free Condition clause requires that all work, materials, or property provided under a contract remain free from any liens or claims by third parties. In practice, this means the contractor or supplier must ensure that subcontractors, laborers, and material providers are fully paid and do not file liens against the property or project. This clause protects the property owner or client from legal claims or encumbrances that could arise due to unpaid debts related to the project, ensuring clear title and preventing potential delays or financial liabilities.
Lien Free Condition. Licensee shall not cause or permit any liens to be placed against the Premises or against Licensor's other property as a result of Licensee's exercise of rights under this License. In the event of the filing of any such liens, Licensee shall promptly cause such liens to be removed. In no event shall such lien removal require more than thirty (30) days.
Lien Free Condition. Licensee shall not cause or permit any liens to be placed against the Premises or against Licensor's other property as a result of Licensee's exercise of rights under this License. In the event of the filing of any such liens, Licensee shall promptly cause
Lien Free Condition. SUNESYS shall not cause or permit any liens to be placed against the RCTC Facility or against RCTC’s other property as a result of construction, installation, or maintenance by or behalf of SUNESYS. In the event of the filing of any such liens, SUNESYS shall promptly (but in no event more than thirty (30) days) cause such liens to be removed or bonded off the RCTC Facility.
Lien Free Condition. University shall not cause or permit any liens to be placed against the Premises or against Owner's other property as a result of University's exercise of rights under this RUA. In the event of the filing of any such liens, University shall promptly cause such liens to be removed.
Lien Free Condition. Icarus shall not cause or permit any liens to be placed against the PV/T System or any components thereof, against the Premises or against City’s other property as a result of Icarus’s exercise of rights under this Agreement. In the event of the filing of any such liens, Icarus shall promptly cause such liens to be removed. To the extent required by Civil Code section 9550 et seq., Icarus shall procure a payment bond for work performed on City property.
Lien Free Condition. Completion of any work described herein in a “Lien-Free Condition” will be deemed to have occurred only upon the earlier to occur of (a) expiration of the applicable statutory periods within which valid construction, mechanics or materialmen’s liens may be recorded and served by reason of design, supply, or construction of such work, with any such liens that have been filed having been released, discharged of record, or bonded as required under the terms of Section 3.04(c) of the Ground Lease, or (ii) the receipt by the Authority of executed unconditional lien waivers and releases on final payment, in form reasonably satisfactory to the Authority, from all Persons then entitled to record liens against the Premises with respect to any aspect of the Work.