Liquidated Damages for Delay Clause Samples
The Liquidated Damages for Delay clause establishes a predetermined amount of compensation that a contractor or party must pay if they fail to complete a project or deliver goods or services by an agreed-upon deadline. Typically, this clause specifies a daily or weekly rate that accrues for each period of delay beyond the scheduled completion date, providing a clear financial consequence for late performance. Its core function is to incentivize timely completion and to provide certainty for both parties by quantifying potential losses in advance, thereby avoiding disputes over actual damages caused by delays.
POPULAR SAMPLE Copied 327 times
Liquidated Damages for Delay. In addition to the Contractor bearing the actual cost of correcting any non-compliant work or any other actual damages resulting from Contractor’s breach of this Agreement, the Contractor agrees to pay the Contractor delay damages in the amount of $500.00 per day for every day that the goods and/or services to be provided pursuant to this Agreement have not been timely delivered to the District in compliance with the Scope of Services set forth above, unless the delay has been properly excused by the terms of this Agreement. The parties agree that the District’s actual damages for delay are difficult to estimate and that this $500.00 per day sum is a reasonable pre-estimate of the District’s actual damages for each day of delay and that the is $500.00 per day sum is intended by the parties to be in the nature of liquidated damages, not a penalty. It is not the parties’ intent for this provision to limit either party’s remedies against the other for the breach of this Agreement, except for the District’s money damages for unexcused delays caused by the Contractor.
Liquidated Damages for Delay. If the Contractor shall fail to complete the Works within the time for completion prescribed in the Contract, or any extended time for completion in accordance with the Contract, then the Contractor shall pay to the Employer the sum specified in the Contract as liquidated damages, for the delay between the time prescribed in the Contract or the extended time for completion, as the case may be, and the date of substantial completion of the Works as stated in the Certificate of Substantial Completion, subject to the applicable limit stated in the Contract. The said sum shall be payable by the sole fact of the delay without the need for any previous notice or any legal proceedings, or proof of damage, which shall in all cases be considered as ascertained. The Employer may, without prejudice to any other method of recovery, deduct the amount of such liquidated damages from any monies in its hands due or which may become due to the Contractor. The payment or deduction of such damages shall not relieve the Contractor from his obligation to complete the Works or from any other of his obligations and liabilities under the Contract. If, before the time for completion of the whole of the Works or of a Section of the Works, a Certificate of Substantial Completion has been issued for any part or Section of the Works, the liquidated damages for delay in completion of the remainder of the Works or of that Section may, for any period of delay after the date stated in such Certificate of Substantial Completion, and in the absence of alternative provisions in the Contract, be reduced in the proportion which the value of the part or Section so certified bears to the total value of the whole of the Works or Section, as applicable. The provisions of this Sub-Clause shall only apply to the rate of liquidated damages and shall not affect the limit thereof. CERTIFICATE OF SUBSTANTIAL COMPLETION When the whole of the Works have been substantially completed and have satisfactorily passed any test on completion prescribed by the Contract, the Contractor may give a notice to that effect to the Engineer accompanied by an undertaking to finish any outstanding work during the Defects Liability Period. Such notice and undertaking shall be in writing and shall be deemed to be a request by the Contractor, for the Engineer to issue a Certificate of Substantial Completion in respect of the Works. The Engineer shall, within twenty-one (21) days of the date of delivery of such notice either i...
Liquidated Damages for Delay. 18.1 If the Contractor fails to complete delivery within the time or times specified in the Contract, Crown Agents may, at its option, acting on behalf of the Principal or the End-User, recover from the Contractor as a debt or deduct from any payment owed to the Contractor one per cent of the value of the Goods which are delayed per week by way of liquidated damages up to a maximum of ten per cent of the value of the Goods.
18.2 If the Contractor fails to complete the performance of all the Services within the time specified in the Contract, Crown Agents may, at its option, acting on behalf of the Principal or the End-User, recover from the Contractor as a debt or deduct from any payment owed to the Contractor one per cent of the value of the Services which are delayed per week by way of liquidated damages up to a maximum of ten per cent of the value of the Services
18.3 The parties confirm that the sums referred to in clauses 18. 1 and 18.2 represent a genuine pre-estimate of the Principal’s or End-User’s loss.
18.4 The Contractor shall not be liable to pay liquidated damages pursuant to this clause 18 where delay in delivery of the Goods or delay in performance of the Services has been caused by Crown Agents, the End- User or the Principal preventing the Contractor from delivering the Goods or performing the Services.
18.5 The Contractor shall not be liable to pay liquidated damages pursuant to this clause 18 where delay in delivery of the Goods or in the performance of the Services is as a result of a Force Majeure event or situation.
18.6 Without prejudice to the provisions of clause 11.6, the Contractor shall have no liability for liquidated damages under this clause 18 in respect of any Contract on FOB/FAS/FCA terms for any period during which the Goods are packed and ready for despatch but cannot be shipped because of a lack of shipping opportunities or similar cause.
18.7 If Crown Agents exercises its rights under clause 18.1 and/or clause 18.2, it shall not be entitled to any of the remedies set out in clause 17.1 (b) to (d) inclusive or in clause 17.3 in respect of the Goods’ late delivery or the Services’ late performance (but such remedies shall be available in respect of the Goods’ condition and in respect of the standards to which the Services are performed).
18.8 Crown Agents shall have the right to recover or deduct liquidated damages from the Contractor in accordance with this clause 18 notwithstanding the termination of the Contract.
Liquidated Damages for Delay. In the event of a delay to the agreed Delivery times, as may be extended in accordance with the Contract, which is attributable to Metso Outotec, Purchaser shall, to the exclusion of all further rights and remedies of Purchaser for such delay, be entitled to claim liquidated damages of delay 0.5% of the Contract Price of the delayed Services and Deliverables, or 0.25% of the Contract Price if not individually priced, for every full week of delay, up to an aggregate maximum of 5% of the Contract Price. Purchaser and Metso Outotec acknowledge and agree that (i) the above liquidated damages represent a genuine pre-estimate of the potential loss suffered by Purchaser as a result of delay caused by Metso Outotec, and do not constitute a penalty, and (ii) save as specified in this clause, Metso Outotec shall not be liable for any delay in meeting any other date or milestone specified in the Contract or elsewhere, and (iii) any delay claim must be made within thirty days from Delivery.
Liquidated Damages for Delay. In addition to the Contractor bearing the actual cost of correcting any non-compliant work or any other actual damages resulting from Contractor’s breach of this Agreement, the Contractor agrees to pay the Contractor delay damages in the amount of [INSERT AMOUNT] per day for every day that the goods and/or services to be provided pursuant to this Agreement have not been timely delivered to the District in compliance with the Scope of Services set forth above, unless the delay has been properly excused by the terms of this Agreement. The parties agree that the District’s actual damages for delay are difficult to estimate and that this [INSERT AMOUNT] per day sum is a reasonable pre-estimate of the District’s actual damages for each day of delay and that the [INSERT AMOUNT] per day sum is intended by the parties to be in the nature of liquidated damages, not a penalty. It is not the parties’ intent for this provision to limit either party’s remedies against the other for the breach of this Agreement, except for the District’s money damages for unexcused delays caused by the Contractor.
Liquidated Damages for Delay. The time limit being essential to and of the essence of this Contract, the Contractor hereby agrees that the TOWN DISTRICT shall be, and is hereby authorized to deduct and retain out of the money which may be due or may become due to said Contractor under this agreement, the sum of FIVE HUNDRED DOLLARS ($500.00) per day, which amount is hereby agreed upon, fixed and determined by the parties hereto as the LIQUIDATED DAMAGES, including overhead charges, services, inspector's wages, and interest on the money invested, that the TOWN DISTRICT will suffer by reason of such default, for each and every day during which the aforesaid work may be incomplete over and beyond the time herein stipulated for its completion, provided, however, that the TOWN DISTRICT shall have the right to extend the time for the completion of said work.
Liquidated Damages for Delay a. Owner and Private Entity recognize that time is of the essence in the completion of the Work and that Owner may suffer loss or damages if the Work is not completed within the period of time stipulated, plus any extensions thereof allowed in accordance with the Agreement. The parties also recognize the delays, expense, and difficulties involved in proving the actual loss or damages suffered by Owner if the Work is not completed on time. Accordingly, if such Work is not fully and satisfactorily completed within the period of time set forth in this Agreement, the Private Entity agrees it shall owe to and pay to Owner as liquidated damages for loss of Owner's use or occupancy of the Work, but not as a penalty, the sum of Two Thousand Dollars ($2,000) as step one liquidated damages for each and every consecutive calendar day of unexcused delay after the date established for Substantial Completion. Once the Work is Substantially Complete, the accrual of step one liquidated damages shall stop and the Private Entity shall have sixty (60) calendar days in which to achieve Final Completion of the Work. If Final Completion of the Work is not achieved by the 60th day after Substantial Completion has been achieved, and if no extension of such time period has been granted by the Owner as required by this Agreement, then Private Entity shall owe the Owner the additional amount of step 2 liquidated damages as set forth in “b” below.
b. The Private Entity agrees it shall owe to and pay to Owner as liquidated damages the sum of One Thousand Dollars ($1,000) as step two liquidated damages for each consecutive calendar day during which full and satisfactory completion of the Work is delayed or exceeds the number of days provided for in this Agreement to complete the Work. Private Entity further agrees that any liquidated damages Owner assesses against Private Entity may also be withheld by Owner from any retainage or other sums Owner may otherwise owe to Private Entity. Private Entity hereby waives any defense as to the validity of any liquidated damages on the grounds such liquidated damages could be void as penalties or are not reasonably related to actual damages except as to whether Private Entity is not responsible for delays. In any event, the amount of liquidated damages which may be assessed under this Agreement shall not exceed $100,000. All such liquidated damages are in addition to any other damages other than for delay that the Owner may be entitled to recover ...
Liquidated Damages for Delay. If the COD has not occurred by the Guaranteed Completion Date, Licensee shall pay the Judicial Council as liquidated damages the amount of three hundred dollars ($300) for each calendar day (or part day) after the Guaranteed Completion Date until such time that the COD occurs. If COD has not occurred within ninety (90) calendar days of the Guaranteed Completion Date, the Judicial Council reserves the right to terminate this SLA by written notice to Licensee. The Judicial Council shall retain any Transaction Fee paid or due as of the date of such termination notice, and Licensee shall comply with Section 11.1 and neither Party shall have any further obligation to the other Party.
Liquidated Damages for Delay. In the event of a delay to the agreed Delivery times, as may be extended in accordance with the Contract, which is attributable to Metso, Purchaser shall, to the exclusion of all further rights and remedies of Purchaser for such delay, be entitled to claim liquidated damages of delay 0.5% of the Contract Price of the delayed Services and Deliverables, or 0.25% of the Contract Price if not individually priced, for every full week of delay, up to an aggregate maximum of 5% of the Contract Price. Purchaser and Metso acknowledge and agree that (i) the above liquidated damages represent a genuine pre-estimate of the potential loss suffered by Purchaser as a result of delay caused by ▇▇▇▇▇, and do not constitute a penalty, and (ii) save as specified in this clause, Metso shall not be liable for any delay in meeting any other date or milestone specified in the Contract or elsewhere, and (iii) any delay claim must be made within thirty days from Delivery.
Liquidated Damages for Delay. Time is of the essence of this Contract. If Contractor shall neglect, fail or refuse to complete its work by the date specified, then Contractor does hereby agree, as part of the consideration for the award of this Contract, to pay to District, as liquidated damages and not as penalty, the sum of $ per day for each calendar day beyond the specified completion date the Contractor fails to complete the work. The parties agree to this arrangement due to the impracticability and difficulty in ascertaining the true value of the damages the District will incur as a result of such delay, and said sum per day is agreed to be a reasonable estimate of the amount of such damages which District will sustain. The parties further agree that such liquidated damages shall be deducted from any amounts owing to Contractor, and if such amounts owing are insufficient, the Contractor shall pay to District the amount of the difference.