Delay Liquidated Damages Clause Samples
The Delay Liquidated Damages clause establishes a predetermined financial penalty that a contractor or party must pay if they fail to complete a project or deliver goods and services by an agreed-upon deadline. Typically, the clause specifies a fixed amount or a daily rate for each day the completion is delayed beyond the contractual date. This mechanism provides certainty for both parties by quantifying the consequences of delay in advance, thereby encouraging timely performance and compensating the non-breaching party for potential losses without the need to prove actual damages.
POPULAR SAMPLE Copied 326 times
Delay Liquidated Damages. Delay Liquidated Damages has the meaning set out in GC 7.6.1.
Delay Liquidated Damages. 7.6.1 The Contractor acknowledges and agrees that the Owner will suffer financial Loss if the Work is not completed within the time specified in the Agreement. The Contractor also recognizes the delays, costs and difficulties involved in proving the actual Loss suffered by the Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, the Contractor agrees that if the date of Substantial Performance of the Work is delayed past the Scheduled Date for Substantial Performance of the Work, subject to any adjustment in Contract Time as provided for in the Agreement, the Contractor shall pay Owner liquidated damages in the amount designated in row B.6 of the Information Sheet (“Delay Liquidated Damages”) for each and every Calendar Day or Working Day, as applicable, of delay until the Contractor has attained Substantial Performance of the Work. The Contractor further expressly acknowledges and agrees that Delay Liquidated Damages payable by the Contractor are:
Delay Liquidated Damages. If Substantial Completion occurs after the Guaranteed Substantial Completion Date, Contractor shall pay to Owner the amounts listed in Attachment T per Day for each Day, or portion thereof, of delay until Substantial Completion occurs (the “Delay Liquidated Damages”).
Delay Liquidated Damages. If Substantial Completion of an applicable Subproject occurs after the applicable Guaranteed Substantial Completion Date, Contractor shall pay to Owner the amounts listed in Attachment T per Day for each Day, or portion thereof, of delay until Substantial Completion of such Subproject occurs (the “Delay Liquidated Damages”).
Delay Liquidated Damages. Subject to Section 20.2C, Contractor’s maximum liability to Owner for (i) Delay Liquidated Damages for Subproject 1 is *** U.S. Dollars (U.S.$***), in the aggregate, and (ii) Delay Liquidated Damages for Subproject 2 is *** U.S. Dollars (U.S.$***), in the aggregate.
Delay Liquidated Damages. (a) The Parties agree that it would be extremely difficult and impracticable under presently known and anticipated facts and circumstances to ascertain and fix the actual damages Owner would incur if Contractor does not achieve Substantial Completion of Unit 6 by the Guaranteed Substantial Completion Date for Unit 6 (as the Guaranteed Substantial Completion Date for Unit 6 may be extended due to Force Majeure, Owner caused delays, differing site conditions, discovery of Hazardous Materials, Changes in Law, or as otherwise contemplated in this Agreement), and, accordingly, if Contractor does not achieve Substantial Completion of Unit 6 by that date, subject to Section 12.1(c) below, Owner’s sole and exclusive remedy for such delay shall be to recover from Contractor as liquidated damages, and not as a penalty, the Delay Liquidated Damages for each Day that Substantial Completion of Unit 6 is delayed beyond the Guaranteed Substantial Completion Date for Unit 6; provided, that in no event shall the aggregate Delay Liquidated Damages for ▇▇▇▇ ▇ exceed its Delay Liquidated Damages Cap.
(b) The Parties agree that it would be extremely difficult and impracticable under presently known and anticipated facts and circumstances to ascertain and fix the actual damages Owner would incur if (i) ▇▇▇▇ ▇ Scrubber Tie-In does not commence by the Guaranteed Tie-In Commencement Date, (ii) Contractor does not complete the successful tie-in of the Unit 5 Scrubber by the Guaranteed Tie-In Completion Date or (iii) after the successful Tie-In of the Unit 5 Scrubber, Contractor does not achieve Substantial Completion of the Unit 5 Scrubber by the Guaranteed Substantial Completion Date (in each case, as the Guaranteed Tie-In Commencement Date, the Guaranteed Tie-in Completion Date or the Guaranteed Substantial Completion Date of the Unit 5 Scrubber, as applicable, may be extended due to Force Majeure, Owner caused delays, differing site conditions, discovery of Hazardous Materials, Changes in Law, or as otherwise contemplated in this Agreement), and, accordingly, upon the occurrence of either event, subject to Section 12.1(c) below, Owner’s sole and exclusive remedy therefore shall be to recover from Contractor as liquidated damages, and not as a penalty, the Delay Liquidated Damages for each Day after the Guaranteed Tie-In Commencement Date that Unit 5 Scrubber Tie-In does not commence, each Day after the Guaranteed Tie-In Completion Date that the successful Tie-In of the Unit 5 Sc...
Delay Liquidated Damages. Subject to Section 20.2C, Contractor’s maximum liability to Owner for Delay Liquidated Damages is *** U.S. Dollars (U.S.$***), in the aggregate.
Delay Liquidated Damages. Contractor agrees that Substantial Completion is not achieved by the Guaranteed Substantial Completion Date, then Contractor shall pay the amount of Delay Liquidated Damages set out the definition thereof to Owner for each day beginning on the first day after the Guaranteed Substantial Completion Date up to but not including the Substantial Completion Date. Contractor shall pay the net amount (if any) of Delay Liquidated Damages to Owner, subject to the limitations set forth in Article 29, and such amount shall be due and payable within twenty-five (25) days after Contractor’s receipt of Owner’s invoice for such net amount submitted at the end of the month following the Guaranteed Substantial Completion Date.
Delay Liquidated Damages. Except as may be otherwise agreed in a Purchase Order, if Delivery of the Equipment has not occurred by the Guaranteed Delivery Date for reasons that are not excused hereunder, and Buyer can prove that as a direct result thereof it must pay delay liquidated damages to its Customer, Supplier shall reimburse Buyer for such delay liquidated damages (such reimbursement not to exceed an amount equal to 0.5% of the price set forth in the Purchase Order allocable to the delayed Equipment for every completed week of delay) for each completed week after the Guaranteed Delivery Date that Buyer pays such liquidated damages to its Customer as a result of Supplier’s delay, provided, however, that the amount of delay liquidated damages payable by Supplier shall be reduced by any amounts received by Buyer under any delay in startup insurance policies providing coverage for any such losses or damages. Payment of the delay liquidated damages shall be the sole and exclusive remedy of Buyer for delay and under no circumstances shall the total aggregate liability of Supplier exceed five percent (5%) of the price set forth in the applicable Purchase Order.
Delay Liquidated Damages. 16.1 Provider warrants that Services will be rendered to Company and within the Time Schedule set out in DDO.
16.2 When there is delay in the Time Schedule, Company shall be entitled to payment of delay damages by Provider for this default equal to the percentage specified in Part A. The total amount of delay damages due under this Clause shall not exceed the amount specified in Part A.
16.3 For the avoidance of doubt, these delay damages shall be the only damages due from the Provider to the Provider’s failure to comply with the Time Schedule. These delay damages shall not preclude termination or remedies for other breaches under the Contract and shall not relieve the Provider from the obligation to complete the Services or from other duties, obligations or responsibilities which the Provider may have under or in connection with the Contract.
16.4 This Clause shall not limit the Provider’s liability for delay damages in any case of fraud, gross negligence, deliberate default or reckless misconduct by the Provider.
16.5 If Provider has not provided a Service by the date on which Company has become entitled to the maximum amount of liquidated damages for that Service, Company may cancel the DDO with respect to the delayed Service. In that case, Provider shall have no claim against Company, and Company shall be entitled to delay damages accumulated through the date of cancellation, plus any reasonable and documented higher charges incurred due to procurement of the Services through a different provider of its own choice, reserving the right to claim from the Provider any reasonable and documented higher charges incurred, due to the default of the Provider.
16.6 If during a period of one year, Company has become entitled to an amount of liquidated damages that exceeds 5% of value of DDOs issued during that year in execution of Local Activation Letter in a certain Country, Company may immediately terminate the Local Activation Letter in the relevant Country without any liability or penalty, applicable against it. In this case, any outstanding liquidated damages due to EGP or an Enel Affiliate by the Provider must be paid at once.
16.7 Delay Damages are payable by Provider within 10 days of receipt of the relevant invoice from the Company. In the event that delay damages are not paid on time, Company may set them off against any amount due by Company to Provider.