Materials Stored. If periodic payments are made on account of materials delivered and suitably stored at the site but not incorporated in the work, they shall, if required by the Board, Program Manager or the Design Professional, be conditional upon submission by the CMR of bills of sale or such other procedure as will establish the Board’s title to such material or otherwise adequately protect the Board’s interest. The CMR is responsible for the existence, protection, and, if necessary, replacement of materials until issuance of the Final Certificate by the Design Professional and Board . The Board shall not pay for any materials stored off site.