Meter Accuracy. All metering equipment measuring the output of the Plant shall be tested at least every six months, at the Buyer’s expense, in accordance with Prudent Operating Practice. At any reasonable time, either Party may request a test of the accuracy of any metering equipment. Each Party shall bear the cost of a test requested by it. The results of meter calibrations or tests shall be available for examination by the Parties at all reasonable times. If, at any time, any metering equipment is found to be inaccurate by more than one-half of one percent (0.5%), the Buyer shall cause such metering equipment to be made accurate or replaced as soon as possible. Each Party shall be given reasonable advance notice of and have the right to be present at the breaking of the seals, testing, calibration and sealing of meters. If either Party believes that there has been a meter failure or stoppage, it shall immediately notify the other Party. The Party owning the meters will then investigate and take corrective action if necessary.
Appears in 2 contracts
Meter Accuracy. All metering equipment measuring the output of the Plant Facility shall be tested at least every six monthsonce annually, at the BuyerSeller’s expense, in accordance with Prudent Operating Good Utility Practice. At any reasonable time, either Party may request a test of the accuracy of any metering equipment. Each Party shall bear the cost of a test requested by it. The results of meter calibrations or tests shall be available for examination by the Parties at all reasonable times. If, at any time, any metering equipment is found to be inaccurate by more than one-half of one percent (0.5%), the Buyer Seller shall cause such metering equipment to be made accurate or replaced as soon as possible. Each Party shall be given reasonable advance notice of and have the right to be present at the breaking of the seals, testing, calibration and sealing of meters. If either Party believes that there has been a meter failure or stoppage, it shall immediately notify the other Party. The Party owning the meters will then investigate and take corrective action if necessary.
Appears in 2 contracts
Meter Accuracy. All metering equipment measuring the output of the Plant shall be tested at least every six months, at the Buyer’s expenseannually, in accordance with Prudent Operating Practice. At any reasonable time, either Party may request a test of the accuracy of any metering equipment. Each Party shall bear the cost of a test requested by it. The results of meter calibrations or tests shall be available for examination by the Parties at all reasonable times. If, at any time, any metering equipment is found to be inaccurate by more than one-half of one percent (0.5%), the Buyer shall cause such metering equipment to be made accurate or replaced as soon as possible. Each Party shall be given reasonable advance notice of and have the right to be present at the breaking of the seals, testing, calibration and sealing of meters. If either Party believes that there has been a meter failure or stoppage, it shall immediately notify the other Party. The Party owning the meters will then investigate and take corrective action if necessary.
Appears in 1 contract
Sources: Power Purchase Agreement
Meter Accuracy. All metering equipment measuring the output of the Plant Facility shall be tested at least every six monthsannually, at the Buyer’s 's expense, in accordance with Prudent Operating Good Utility Practice. At any reasonable time, either Party may request a test of the accuracy of any metering equipment. Each Party shall bear the cost of a test requested by it. The results of meter calibrations or tests shall be available for examination by the Parties at all reasonable times. If, at any time, any metering equipment is found to be inaccurate by more than that one-half of one percent (0.5%), the The Buyer shall cause such metering equipment to be made accurate or replaced as soon as possible. Each Party shall be given reasonable advance notice of and have the right to be present at the breaking of the seals, testing, calibration and sealing of meters. If either Party believes that there has been a meter failure or stoppage, it shall immediately notify the other Party. The Party owning the meters will then investigate and take corrective action if necessary.
Appears in 1 contract
Sources: Power Purchase Agreement
Meter Accuracy. All metering equipment measuring the output of the Plant Facility shall be tested at least every six monthsannually, at the Buyer’s 's expense, in accordance with Prudent Operating Good Utility Practice. At any reasonable time, either Party may request a test of the accuracy of any metering equipment. Each Party shall bear the cost of a test requested by it. The results of meter calibrations or tests shall be available for examination by the Parties at all reasonable times. If, at any time, any metering equipment is found to be inaccurate by more than one-half of one percent (0.5%), the The Buyer shall cause such metering equipment to be made accurate or replaced as soon as possible. Each Party shall be given reasonable advance notice of and have the right to be present at the breaking of the seals, testing, calibration and sealing of meters. If either Party believes that there has been a meter failure or stoppage, it shall immediately notify the other Party. The Party owning the meters will then investigate and take corrective action if necessary.
Appears in 1 contract
Sources: Power Purchase Agreement
Meter Accuracy. All metering equipment measuring the output of the Plant Facility shall be tested at least every six monthsannually, at the BuyerSeller’s expense, in accordance with Prudent Operating Good Utility Practice. At any reasonable time, either Party may request a test of the accuracy of any metering equipment. Each Party shall bear the cost of a test requested by it. The results of meter calibrations or tests shall be available for examination by the Parties at all reasonable times. If, at any time, any metering equipment is found to be inaccurate by more than that one-half of one percent (0.5%), the Buyer Seller shall cause such metering equipment to be made accurate or replaced as soon as possible. Each Party shall be given reasonable advance notice of and have the right to be present at the breaking of the seals, testing, calibration and sealing of meters. If either Party believes that there has been a meter failure or stoppage, it shall immediately notify the other Party. The Party owning the meters will then investigate and take corrective action if necessary.
Appears in 1 contract
Sources: Power Purchase Agreement
Meter Accuracy. All metering equipment measuring the output of the Plant Facility shall be tested at least every six monthsannually, at the BuyerSeller’s expense, in accordance with Prudent Operating Good Utility Practice. At any reasonable time, either Party may request a test of the accuracy of any metering equipment. Each Party shall bear the cost of a test requested by it. The results of meter calibrations or tests shall be available for examination by the Parties at all reasonable times. If, at any time, any metering equipment is found to be inaccurate by more than one-half of one percent (0.5%), the Buyer Seller shall cause such metering equipment to be made accurate or replaced as soon as possible. Each Party shall be given reasonable advance notice of and have the right to be present at the breaking of the seals, testing, calibration and sealing of meters. If either Party believes that there has been a meter failure or stoppage, it shall immediately notify the other Party. The Party owning the meters will then investigate and take corrective action if necessary.
Appears in 1 contract
Sources: Power Purchase Agreement