Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 112 contracts
Sources: Contract Agreement, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 38 contracts
Sources: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 22 contracts
Sources: Engineering Procurement and Construction (Epc) Agreement, Contract Agreement, Contract Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor theContractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 7 contracts
Sources: Engineering Procurement and Construction (Epc) Agreement, Construction Contract, Contract Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Authority‟s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Authority‟s Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 6 contracts
Sources: Engineering, Procurement and Construction Agreement, Construction Contract, Epc Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Employer's Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Employer's Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 3 contracts
Sources: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic traffic, parking management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 3 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s 's Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s 's Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 3 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 2 contracts
Sources: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent comments, if any, to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete trafficmanagementandmeasuresforensuringsafety.TheAuthority’sEngineershallcomplete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 2 contracts
Sources: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction (Epc) Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.ensuring
Appears in 2 contracts
Sources: Draft Contract Agreement, Contract Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor theContractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Construction Contract
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.the
Appears in 1 contract
Sources: Contract Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Authority‟s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.ensuring
Appears in 1 contract
Sources: Epc Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Construction Contract
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Employer‟s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Employer‟s Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Epc Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.of
Appears in 1 contract
Sources: Construction Contract
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the AuthorityEmployer’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The AuthorityEmployer’s Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Demonstration Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to before the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management management, and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Engineering Procurement and Construction (Epc) Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of Draft Contract AgreementPage 71 of 261 S-D Tunnel 2022 equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Construction Contract
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of Draft Contract AgreementPage 70 of 145 Aug. 2020 equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Contract Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Authority‟s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Authority‟s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the AuthorityEmployer’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The AuthorityEmployer’s Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of Draft Contract AgreementPage 70 of 146 Jammu-Akhnoor (P-III) Oct 2020 equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s Engineer shall complete the review and convey its consent to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Contract Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the constructionConstruction, submit to the AuthorityEmployer’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The AuthorityEmployer’s Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Epc Contract
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the AuthorityEmployer’s Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic site management and measures for ensuring safety. The AuthorityEmployer’s Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract
Sources: Epc Agreement
Methodology. The Contractor shall, at least 15 (fifteen) days prior to the commencement of the construction, submit to the Authority’s AUTHORITY’S/GMDAs Engineer for review and consent the methodology proposed to be adopted for executing the Works, giving details of equipment to be deployed, traffic management and measures for ensuring safety. The Authority’s AUTHORITY’S/GMDAs Engineer shall complete the review and convey its consent comments to the Contractor within a period of 10 (ten) days from the date of receipt of the proposed methodology from the Contractor.
Appears in 1 contract