Common use of Monitoring and Notification Clause in Contracts

Monitoring and Notification. ‌ Design-Build Contractor is responsible for verifying the progress of each Utility Owner's work and for notifying IFA when Design-Build Contractor has cause to believe that any Utility Owner will fail to meet a deadline determined pursuant to Section 6.8.1. Design-Build Contractor shall notify IFA within two (2) Business Days after discovery of such potential delay.

Appears in 2 contracts

Sources: Public Private Agreement, Public Private Agreement

Monitoring and Notification. Design-Build Contractor is responsible for verifying the progress of each Utility Owner's work and for notifying IFA when Design-Build Contractor has cause to believe that any Utility Owner will fail to meet a deadline determined pursuant to Section 6.8.1. Design-Build Contractor shall notify IFA within two (2) Business Days after discovery of such potential delay.

Appears in 1 contract

Sources: Public Private Agreement