Monthly Status Report. On or before the tenth (10th) Day of each month (unless some other frequency is agreed upon by the Parties), Contractor shall submit to Owners, for Owners’ review and comment, a written status report covering the prior month (a “Monthly Status Report”). The report shall be prepared in an electronic format reasonably acceptable to Owners and substantially in the form of Exhibit W, and shall include (i) a description of the progress of the Work against the Project Schedule, including critical path activities interconnected by schedule logistics, (ii) a statement of significant issues which remain unresolved and Contractor’s recommendations for resolving the same, (iii) a summary of significant Facility events which are scheduled or expected to occur during the following interval, and (iv) additional information reasonably requested by Owners. Such report also shall include any events or circumstances involving Contractor or Subcontractor Personnel reported to Contractor with respect to Work performed at the Site and/or reportable by Contractor to the NRC or another Government Authority along with a listing and discussion of any OSHA reportable injuries for that month for Work performed at the Site. The Project Schedule and Monthly Status Reports shall be available to Owners in paper form, at the Site (following Full Notice to Proceed) or such other location mutually agreed upon by the Parties.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Agreement (Alabama Power Co), Engineering, Procurement and Construction Agreement (Georgia Power Co)