Monthly Updates to CPM Schedule Clause Samples

The "Monthly Updates to CPM Schedule" clause requires the contractor to regularly update the Critical Path Method (CPM) project schedule on a monthly basis. This involves reviewing project progress, incorporating completed work, and adjusting future activities and timelines to reflect any changes or delays. By mandating these updates, the clause ensures that all parties have an accurate and current understanding of the project's status, which helps in identifying potential issues early and facilitates better project management and coordination.
Monthly Updates to CPM Schedule. After approval by Owner of the CPM Performance Measurement Baseline Schedule, Contractor shall manage and update a critical path method schedule for the Work no less frequently than once per Month to reflect the actual progress to date (“Monthly Updated CPM Schedule”); provided, however, this Monthly Updated CPM Schedule shall not modify the CPM Performance Measurement Baseline Schedule, the Key Milestone Schedule, Guaranteed Substantial Completion Date or Required Final Completion Date, nor shall it change any dates that relate to Owner’s obligations under the Agreement. If Contractor changes the schedule logic, any durations or cost-loading with respect to any activity in its Monthly Updated CPM Schedule such that it deviates from the CPM Performance Measurement Baseline Schedule, Contractor shall provide Owner with a written explanation of each such change along with such Monthly Updated CPM Schedule (but the CPM Performance Measurement Baseline Schedule shall not be changed). The Monthly Updated CPM Schedule shall be statused through the date of the applicable Invoice so that the Work represented in the Monthly Updated CPM Schedule matches the Payment Milestones proposed for payment by Contractor in the Invoice. The Monthly Updated CPM Schedule will have attached to it the current CPM Performance Measurement Baseline Schedule for comparison. The Monthly Updated CPM Schedule shall be in the same detail and form as required by the CPM Performance Measurement Baseline Schedule and shall be submitted by Contractor to Owner with each Invoice. Contractor shall promptly correct any errors or inconsistencies in the updates to the Monthly Updated CPM Schedule identified to Contractor by Owner and resubmit a corrected Monthly Updated CPM Schedule for Owner’s review. Owner’s review or approval of any Monthly Updated CPM Schedule shall not relieve Contractor of any obligations for the performance of the Work, change the Key Milestone Schedule, the Guaranteed Substantial Completion Date or the Required Final Completion Date, nor shall it be construed to establish the reasonableness of any Monthly Updated CPM Schedule.
Monthly Updates to CPM Schedule. After acceptance by Owner of the CPM Schedule, Contractor shall manage and update the CPM Schedule no less frequently than once per Month with Primavera Project Planner, using the critical path method, to reflect the actual progress to date (“Monthly Updated CPM Schedule”); provided, however, Contractor may not modify any Key Date without a Change Order executed pursuant to this Agreement, nor shall Contractor change any dates that relate to Owner’s obligations without obtaining Owner’s written consent. The Monthly Updated CPM Schedule shall be in the same detail and form and meet all of the other requirements specified for the CPM Schedule and shall be submitted by Contractor to Owner in native electronic format and hard copy with each Invoice. Contractor shall provide all supporting data reasonably necessary to validate the progress shown in each schedule update including: (a) percent complete curves for the total project, (b) engineering and design, (c) procurement, (d) construction, and (e) start-up and Commissioning. Contractor shall also provide key commodity installation data including: (f) budgeted quantity, (g) current estimated quantity, (h) quantity installed by period, (i) overall quantity installed and forecast to complete to validate claimed overall project completion status. Contractor shall promptly correct any material errors or inconsistencies in the updates to the CPM Schedule identified to Contractor by Owner and resubmit a corrected Monthly Updated CPM Schedule for Owner’s review.
Monthly Updates to CPM Schedule. After approval by Owner of the baseline CPM Schedule, Contractor shall manage and update the CPM Schedule no less frequently than once per Month with the latest release of Microsoft Project to reflect the actual progress to date (“Monthly Updated CPM Schedule”); provided, however, Contractor may not modify any Milestone Schedule Date or any Guaranteed Date without a Change Order being executed pursuant to this Agreement, nor shall Contractor change any dates that relate to Owner’s obligations without obtaining Owner’s written consent. If Contractor changes the schedule activities, logic, durations, codes or cost-loading with respect to any activity, Contractor shall provide Owner with a written explanation of each such change along with such Monthly Updated CPM Schedule. The Monthly Updated CPM Schedule shall be in the same detail and form as required by the CPM Schedule and shall be submitted by Contractor to Owner with each Invoice. Contractor shall promptly correct any errors or inconsistencies in the updates to the CPM Schedule identified to Contractor by Owner and resubmit a corrected Monthly Updated CPM Schedule for Owner’s review.
Monthly Updates to CPM Schedule. After acceptance by Owner of the CPM Schedule, Contractor shall manage and update the CPM Schedule no less frequently than once per Month with Primavera Project Planner, using the critical path method, to reflect the actual progress to date (“Monthly Updated CPM Schedule”); provided, however, Contractor may not modify any Key Date without a Change Order executed pursuant to this Agreement, nor shall Contractor change any dates that relate to Owner’s obligations without obtaining Owner’s written consent. The Monthly Updated CPM Schedule shall be in the same detail and form and meet all of the other requirements specified for the CPM Schedule and shall be submitted by Contractor to Owner in native electronic format and hard copy with each Invoice. Contractor shall provide all supporting data reasonably necessary to validate the progress shown in each schedule update including: (a) percent complete curves for the total project, (b) engineering and design,

Related to Monthly Updates to CPM Schedule

  • Monthly Statement The Contractor shall submit a statement to the Engineer at the end of each month, in a tabulated form approved by the Engineer, showing the amounts to which the Contractor considers himself to be entitled. The statement shall include the following items, as applicable; - the value of the Permanent Work executed up to the end of previous month - such an amount (not exceeding 75 percent of the value) as the Engineer may consider proper on account of materials for permanent work delivered by the Contractor in the site - such amount as the Engineer may consider fair and reasonable for any Temporary Works for which separate amounts are provided in the Bill of Quantities - adjustments under Clause 70 - any amount to be withheld under retention provisions of Sub-clause 60.3 - any other sum to which the Contractor may be entitled under the Contract If the Engineer disagrees with or cannot verify any part of the statement, the Contractor shall submit such further information as the Engineer may reasonably require and shall make such changes and corrections in the statement as may be directed by the Engineer. In cases where there is difference in opinion as to the value of any item, the Engineer’s view shall prevail.

  • SUBMISSION OF THE MONTHLY MI REPORT 4.1 The completed MI Report shall be completed electronically and returned to the Authority by uploading the electronic MI Report computer file to MISO in accordance with the instructions provided in MISO. 4.2 The Authority reserves the right (acting reasonably) to specify that the MI Report be submitted by the Supplier using an alternative communication to that specified in paragraph 4.1 above such as email. The Supplier agrees to comply with any such instructions provided they do not materially increase the burden on the Supplier.

  • Updates to Schedules Should any of the information or disclosures provided on any of the Schedules attached hereto become outdated or incorrect in any material respect, the Borrower shall promptly provide the Agent in writing with such revisions or updates to such Schedule as may be necessary or appropriate to update or correct same; provided, however, that no Schedule shall be deemed to have been amended, modified or superseded by any such correction or update, nor shall any breach of warranty or representation resulting from the inaccuracy or incompleteness of any such Schedule be deemed to have been cured thereby, unless and until the Required Banks, in their sole and absolute discretion, shall have accepted in writing such revisions or updates to such Schedule.

  • Monthly Statements Each month we will send you a statement showing purchases, cash advances, payments, and credits made to your Account during the billing cycle, as well as your “New Balance”, any Finance Charge and any late charges. Your statement also will identify the minimum monthly payment you must make for that billing period and the date it is due. You agree to retain for statement verification copies of transaction slips resulting from each purchase, each advance, and other transactions on your Account. Unless you notify us of a billing error in accordance with the section entitled “Your Billing Rights”, you accept your monthly statement as an accurate statement of your Account with us.

  • Monthly Servicer’s Certificate On or before the Determination Date immediately preceding each Distribution Date, the Servicer shall deliver to the Depositor, the Seller, the Owner Trustee, the Indenture Trustee and each Paying Agent, with a copy to the Rating Agencies, a certificate of a Servicing Officer substantially in the form of Exhibit A (a “Servicer’s Certificate”) and attached to a Servicer’s report containing all information necessary to make the transfers and distributions pursuant to Sections 4.5, 4.6 and 4.7, together with the written statements to be furnished by the Indenture Trustee to the Certificateholders pursuant to Section 4.9 and by the Indenture Trustee to the Noteholders pursuant to Section 4.9 and pursuant to Section 6.6 of the Indenture. The Servicer shall separately identify (by account number) in a written notice to the Depositor, the Owner Trustee and the Indenture Trustee the Receivables to be repurchased by the Depositor or to be purchased by the Servicer, as the case may be, on the Business Day preceding such Distribution Date, and, upon request of one of the foregoing parties, each Receivable which became a Defaulted Receivable during the related Collection Period. The Servicer shall deliver to the Rating Agencies any information, to the extent it is available to the Servicer, that the Rating Agencies reasonably request (and the initial Servicer shall specify in writing to the successor Servicer any such requests that remain unsatisfied during the servicing transition to the successor Servicer) in order to monitor the Trust.