Common use of Negotiated Option Clause in Contracts

Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner is responsible for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.

Appears in 29 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Transmission Owner’s Provider's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of the Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.

Appears in 14 contracts

Sources: Qualifying Facility Large Generator Interconnection Agreement, Qualifying Facility Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.35.1.2, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Transmission Owner’s 's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner is responsible for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.

Appears in 8 contracts

Sources: Settlement Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damagesdates, the provision of incentives or the procurement and construction of a portion of the Transmission Owner’s Provider's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of the Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.

Appears in 6 contracts

Sources: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

Negotiated Option. If the Interconnection Customer elects not to exercise its option under Article 5.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner is responsible for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.

Appears in 6 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Transmission OwnerProvider’s Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of the Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of the Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.

Appears in 2 contracts

Sources: Small Generator Interconnection Agreement (Sgia), Interconnection Agreement (Renegy Holdings, Inc.)

Negotiated Option. If the Interconnection Customer elects not to exercise its option under Article 5.1.3, 5.1.3 (Option to Build), Interconnection Customer shall so notify Transmission Provider and Interconnecting Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Interconnecting Transmission Owner is responsible for the design, procurement and construction of the Interconnecting Transmission Owner’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Interconnecting Transmission Owner shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.Interconnecting Transmission

Appears in 2 contracts

Sources: Service Agreement, Service Agreements

Negotiated Option. If Interconnection Customer elects not to exercise its the written option provided by Transmission Provider under Article 5.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damagesdates, the provision of incentives or the procurement and construction of a portion of the Transmission Owner’s Provider's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of the Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.

Appears in 1 contract

Sources: Large Generator Interconnection Agreement (Lgia)

Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Transmission Owner’s Provider's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of the Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.Provider's

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement (Lgia)

Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.35.1.2, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Transmission Owner’s 's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner is responsible for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades pursuant to Article 5.1.1, Standard Option.

Appears in 1 contract

Sources: Interim Generator Interconnection Agreement

Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damagesdates, the provision of incentives or the procurement and construction of a portion of the Transmission OwnerProvider’s Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of the Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of the Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.

Appears in 1 contract

Sources: Large Generator Interconnection Agreement (Lgia)