Common use of Negotiated Option Clause in Contracts

Negotiated Option. If the dates designated by Interconnection Customer are not acceptable to Interconnecting Transmission Owner, the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives, or the procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build under Article 5.1.3). If the Parties are unable to reach agreement on such terms and conditions, then, pursuant to Article 5.1.1 (Standard Option), Interconnecting Transmission Owner shall assume responsibility for the design, procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build.

Appears in 9 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Negotiated Option. If the dates designated by the Interconnection Customer are not acceptable to Interconnecting Transmission Ownerthe CAISO and Participating TO, the Parties shall in good faith attempt to negotiate terms and conditions (conditions, including revision of the specified dates and liquidated damages, the provision of incentives, or the procurement and construction of all facilities other than the Interconnecting Transmission OwnerParticipating TO’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build under Article 5.1.3). If the Parties are unable to reach agreement on such terms and conditions, then, pursuant to Article 5.1.1 (Standard Option), Interconnecting Transmission Owner the Participating TO shall assume responsibility for the design, procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Participating TO's Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build.

Appears in 8 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Negotiated Option. If the dates designated by Interconnection Customer pursuant to Article 5.1 are not acceptable to Interconnecting Transmission Owner, the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives, or the procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build under Article 5.1.3). If the Parties are unable to reach agreement on such terms and conditions, then, pursuant to Article 5.1.1 (Standard Option), Interconnecting Transmission Owner shall assume responsibility for the design, procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects has elected to exercise the Option to Build. Transmission Owner and Interconnection Customer may adopt an incentive payment schedule that is mutually agreeable to encourage Transmission Owner to meet specified accelerated dates. Such payment by Interconnection Customer is not subject to refund.

Appears in 8 contracts

Sources: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)

Negotiated Option. If the dates designated by Interconnection Customer pursuant to Article 5.1 are not acceptable to Interconnecting Transmission Owner, the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives, or the procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build under Article 5.1.3). If the Parties are unable to reach agreement on such terms and conditions, then, pursuant to Article 5.1.1 (Standard Option), Interconnecting Transmission Owner shall assume responsibility for the design, procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects has elected to exercise the Option to Build.

Appears in 8 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Negotiated Option. If the dates designated by Interconnection Customer are not acceptable to Interconnecting the Connecting Transmission Owner, the Parties Interconnection Customer and Connecting Transmission Owner shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives, incentives or the procurement and construction of all facilities other than the Interconnecting Connecting Transmission Owner’s Interconnection Attachment Facilities and Stand Alone Network Upgrades System Upgrade Facilities if the Interconnection Customer elects to exercise the Option to Build under Article 5.1.3). If the two Parties are unable to reach agreement on such terms and conditions, then, pursuant to Article 5.1.1 (Standard Option), Interconnecting Connecting Transmission Owner shall assume responsibility for the design, procurement and construction of all facilities other than the Interconnecting Connecting Transmission Owner’s Interconnection Attachment Facilities and Stand Alone Network Upgrades System Upgrade Facilities if the Interconnection Customer elects to exercise the Option to Build.

Appears in 6 contracts

Sources: Standard Interconnection Agreement, Standard Interconnection Agreement, Engineering & Procurement Agreement

Negotiated Option. If the dates designated by Interconnection Customer pursuant to Article 5.1 are not acceptable to Interconnecting Transmission Owner, the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives, or the procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build under Article 5.1.3). If the Parties are unable to reach agreement on such terms and conditions, then, pursuant to Article 5.1.1 (Standard Option), Interconnecting Transmission Owner shall assume responsibility for the design, procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build.Alone

Appears in 3 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Negotiated Option. If the designated dates designated by the Interconnection Customer are not acceptable to Interconnecting Transmission Ownerthe CAISO and Participating TO, the Parties shall in good faith attempt to negotiate terms and conditions (conditions, including revision of the specified dates and liquidated damages, the provision of incentives, or the procurement and construction of all facilities other than the Interconnecting Transmission OwnerParticipating TO’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build under Article 5.1.3). If the Parties are unable to reach agreement on such terms and conditions, then, pursuant to Article 5.1.1 (Standard Option), Interconnecting Transmission Owner the Participating TO shall assume responsibility for the design, procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Participating TO's Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build.

Appears in 3 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Negotiated Option. If the dates designated by Interconnection Customer pursuant to Article 5.1 are not acceptable to Interconnecting Transmission Owner, the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives, or the procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build under Article 5.1.3). If the Parties are unable to reach agreement on such terms and conditions, then, pursuant to Article Article 5.1.1 (( Standard Option), Interconnecting Transmission Owner shall assume responsibility for the design, procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects has elected to exercise the Option to Build. Transmission Owner and Interconnection Customer may adopt an incentive payment schedule that is mutually agreeable to encourage Transmission Owner to meet specified accelerated dates. Such payment by Interconnection Customer is not subject to refund.

Appears in 2 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement

Negotiated Option. If the dates designated by Interconnection Customer pursuant to Article 5.1 are not acceptable to Interconnecting Transmission Owner, the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives, or the procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build under Article 5.1.3). If the Parties are unable to reach agreement on such terms and conditions, then, pursuant to Article 5.1.1 (Standard Option), Interconnecting Transmission Owner shall assume responsibility for the design, procurement and construction of all facilities other than the Interconnecting Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades if the Interconnection Customer elects to exercise the Option to Build.

Appears in 1 contract

Sources: Generator Interconnection Agreement