No Time Extensions. Except as otherwise specifically provided in Section 12, TxDOT shall have no obligation to extend a Completion Deadline and Developer shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of each Phase of the Project and complete the Bridge Demolition Work by the applicable Completion Deadlines for any reason.
Appears in 4 contracts
Sources: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement
No Time Extensions. Except as otherwise specifically provided in Section 1213, TxDOT shall have no obligation to extend a Completion Deadline and Developer shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of each Phase of the Project and complete the Bridge Demolition Work by the applicable Completion Deadlines for any reason.
Appears in 4 contracts
Sources: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement
No Time Extensions. Except as otherwise specifically provided in Section 12, TxDOT shall have no obligation to extend a Completion Deadline and Developer shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of each Phase of the Project and complete the Early Bridge Demolition Removal Work by the applicable Completion Deadlines for any reason.
Appears in 2 contracts
Sources: Comprehensive Development Agreement, Comprehensive Development Agreement
No Time Extensions. Except as otherwise specifically provided in Section 12, TxDOT shall have no obligation to extend a Completion Deadline and Developer shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of each Phase of the Project and complete the Bridge Demolition Work by the applicable Completion Deadlines for any reason.
Appears in 2 contracts
Sources: Comprehensive Development Agreement, Comprehensive Development Agreement
No Time Extensions. Except as otherwise specifically provided in Section 12, TxDOT shall have no obligation to extend a Completion Deadline and Developer shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of each Phase of the Project and complete removal of the Existing New Harbor Bridge Demolition Work over the Corpus Christi Shipping Channel by the applicable Completion Deadlines for any reason.
Appears in 1 contract
Sources: Comprehensive Development Agreement