Common use of Non-Network Resource Clause in Contracts

Non-Network Resource. Requests to interconnect the Generating Facility as a non-Network resource shall be studied either (i) pursuant to a Transmission Service Request, so that any necessary Network Upgrades can be identified or (ii) at full output of the proposed Generating Facility with required Network Upgrades identified and to

Appears in 4 contracts

Sources: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)