Operating and Maintenance Manuals. Contractor shall supply Start Up, operation, and maintenance manuals for review by the Owner in accordance with Attachment V of the Agreement. These Start Up manuals will include the sequence of activities that must be carried out in order to Start Up of the Liquefaction Facility. The manuals shall incorporate the DOT Part 193 Operator Qualification and OSHA 1910 requirements that define the process safety management system.
Appears in 4 contracts
Sources: Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC)
Operating and Maintenance Manuals. Contractor shall supply Start Up, operation, and maintenance manuals for review by the Owner in accordance with Attachment V of the Agreement. These Start Up manuals will include the sequence of activities that must be carried out in order to Start Up of the Stage 2 Liquefaction Facility. The manuals shall incorporate the DOT Part 193 Operator Qualification and OSHA 1910 requirements that define the process safety management system.
Appears in 4 contracts
Sources: Lump Sum Turnkey Agreement, Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC)
Operating and Maintenance Manuals. Contractor shall supply Start Up, operation, and maintenance manuals for review by the Owner in accordance with Attachment V of the Agreement. These Start Up manuals will include the sequence of activities that must be carried out in order to Start Up of the Stage 2 Liquefaction Facility. The manuals shall incorporate the DOT Part 193 Operator Qualification and OSHA 1910 requirements that define the process safety management system.
Appears in 4 contracts
Sources: Fixed Price Separated Turnkey Agreement (Cheniere Corpus Christi Holdings, LLC), Fixed Price Separated Turnkey Agreement (Cheniere Energy Inc), Fixed Price Separated Turnkey Agreement (Corpus Christi Pipeline GP, LLC)
Operating and Maintenance Manuals. Contractor shall supply Start Up, operation, and maintenance manuals for review by the Owner in accordance with Attachment V of the Agreement. These Start Up manuals will include the sequence of activities that must be carried out in order to Start Up of the Stage 1 Liquefaction Facility. The manuals shall incorporate the DOT Part 193 Operator Qualification and OSHA 1910 requirements that define the process safety management system.
Appears in 1 contract
Sources: Fixed Price Separated Turnkey Agreement (Cheniere Energy Inc)
Operating and Maintenance Manuals. Contractor shall supply Start Up, operation, and maintenance manuals for review by the Owner in accordance with Attachment V of the Agreement. These Start Up manuals will include the sequence of activities that must be carried out in order to Start Up of the Stage 4 Liquefaction Facility. The manuals shall incorporate the DOT Part 193 Operator Qualification and OSHA 1910 requirements that define the process safety management system.
Appears in 1 contract
Sources: Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC)