Common use of Other TxDOT Approvals Clause in Contracts

Other TxDOT Approvals. 3.1.4.1 Whenever the Contract Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor may deliver to TxDOT a written notice stating the date within which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-Caused Delay for which DB Contractor may be entitled to submit a Claim in accordance with Section 13.3.

Appears in 16 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

Other TxDOT Approvals. 3.1.4.1 3.1.4.1. Whenever the Contract Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 3.1.4.2. If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor may deliver to TxDOT a written notice stating the date within which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-Caused Delay for which DB Contractor may be entitled to submit a Claim in accordance with Section 13.313.3.1.

Appears in 16 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

Other TxDOT Approvals. 3.1.4.1 6.3.4.1 Whenever the Contract CDA Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 6.3.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.26.3.2, then DB Contractor Developer may deliver to TxDOT a written notice stating the date within which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter from and after lapse of the applicable time period under Section 6.3.2 may constitute a TxDOT-Caused Delay for which DB Contractor Developer may be entitled to submit issue a Claim in accordance with Section 13.3Relief Event Notice and Compensation Event Notice under Sections 13.1 and 13.2.

Appears in 16 contracts

Sources: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement

Other TxDOT Approvals. 3.1.4.1 (a) Whenever the Contract Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 (b) If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.24.1.2, then DB Contractor Developer may deliver to TxDOT a written notice stating the date within by which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-Caused Delay for which DB Contractor Developer may be entitled to submit a Claim in accordance with Section 13.312.3.1.

Appears in 15 contracts

Sources: Development Agreement, Development Agreement, Development Agreement

Other TxDOT Approvals. 3.1.4.1 Whenever the Contract Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor Developer may deliver to TxDOT a written notice stating the date within by which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-Caused Delay for which DB Contractor Developer may be entitled to submit a Claim in accordance with Section 13.313.3.1.

Appears in 10 contracts

Sources: Development Agreement, Development Agreement, Development Agreement

Other TxDOT Approvals. 3.1.4.1 3.1.4.1. Whenever the Contract DBA Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 3.1.4.2. If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor may deliver to TxDOT a written notice stating the date within by which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-TxDOT- Caused Delay for which DB Contractor may be entitled to submit a Claim in accordance with Section 13.313.3.1.

Appears in 7 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

Other TxDOT Approvals. 3.1.4.1 6.3.4.1 Whenever the Contract CDA Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 6.3.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.26.3.2, then DB Contractor Developer may deliver to TxDOT a written notice stating the date within which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter from and after lapse of the applicable time period under Section 6.3.2 may constitute a TxDOT-TxDOT- Caused Delay for which DB Contractor Developer may be entitled to submit issue a Claim in accordance with Section 13.3Relief Event Notice and Compensation Event Notice under Sections 13.1 and 13.2.

Appears in 7 contracts

Sources: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement

Other TxDOT Approvals. 3.1.4.1 Whenever the Contract Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor Developer may deliver to TxDOT a written notice stating the date within which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-Caused Delay for which DB Contractor Developer may be entitled to submit a Claim in accordance with Section 13.313.3.1.

Appears in 6 contracts

Sources: Development Agreement, Development Agreement, Development Agreement

Other TxDOT Approvals. 3.1.4.1 Whenever the Contract CDA Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor Developer may deliver to TxDOT a written notice stating the date within which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-TxDOT- Caused Delay for which DB Contractor Developer may be entitled to submit a Claim in accordance with Section 13.313.3.1.

Appears in 4 contracts

Sources: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement

Other TxDOT Approvals. 3.1.4.1 Whenever the Contract Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor Developer may deliver to TxDOT a written notice stating the date within by which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-TxDOT- Caused Delay for which DB Contractor Developer may be entitled to submit a Claim in accordance with Section 13.313.3.1.

Appears in 1 contract

Sources: Development Agreement

Other TxDOT Approvals. 3.1.4.1 Whenever the Contract Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness. 3.1.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor Developer may deliver to TxDOT a written notice stating stati ng the date within by which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-Caused Delay for which DB Contractor Developer may be entitled to submit a Claim Cla im in accordance with Section 13.313.3.1.

Appears in 1 contract

Sources: Development Agreement