Common use of Outage Authority and Coordination Clause in Contracts

Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Parties remove from service any of its respective Interconnection Facilities or Network

Appears in 3 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Parties remove from service any of its respective Interconnection Facilities or Networkof

Appears in 3 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Parties Party remove from service any of its respective Interconnection Facilities or NetworkNetwork Upgrades that may

Appears in 2 contracts

Sources: Standard Large Generator Interconnection Agreement (Lgia), Interconnection Agreement

Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Parties Party remove from service any of its respective Interconnection Facilities or Network

Appears in 2 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement

Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Parties remove from service any of its respective Interconnection Facilities or Networkremove

Appears in 1 contract

Sources: Large Generator Interconnection Agreement

Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Parties remove from service any of its respective Interconnection Facilities or NetworkNetwork Upgrades that may impact another Party's facilities as necessary to perform maintenance or testing or to install or replace equipment. Absent an Emergency Condition, the Party scheduling a

Appears in 1 contract

Sources: Large Generator Interconnection Agreement (Lgia)

Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Parties Party remove from service any of its respective Interconnection Facilities or Networkrespective

Appears in 1 contract

Sources: Qualifying Facility Large Generator Interconnection Agreement (Qf Lgia)