Partial Occupancy. 20.1.1 Owner reserves the right to enter and install equipment within each portion of the Project as it is ready to receive same, upon the condition that ▇▇▇▇ shall not be responsible for equipment so placed other than loss or damage caused by the acts or omissions of ▇▇▇▇ or those in ▇▇▇▇'▇ employ. Such partial occupancy by Owner shall not constitute acceptance of the Project or of work not completed in accordance with the Contract Documents, nor shall it in any way relieve ▇▇▇▇ from correcting defective workmanship or materials in the area where Owner has installed equipment. 20.1.2 Owner reserves the right to take possession of or use all or part of any work prior to completion and final acceptance of all the work. If Owner exercises this right, ▇▇▇▇ shall be relieved of liability for loss or damage to completed portions of the work other than loss or damage caused by the acts, omissions, or breaches of warranty by ▇▇▇▇. Such taking of possession by Owner shall not relieve ▇▇▇▇ from any other provisions of the Contract Documents, shall not constitute a final acceptance of any such work or of work not completed in accordance with the Contract Documents, and shall not relieve ▇▇▇▇ from responsibility for correcting defective workmanship or materials in the area so occupied. 20.1.3 Owner may at any time during the performance of the work enter the work area for the purpose of performing any necessary work by Owner labor or other contractors, and for any other purpose in connection with the installation of facilities. In doing so, Owner shall endeavor not to interfere with ▇▇▇▇, and ▇▇▇▇ shall not interfere with other work being done by or on behalf of Owner.
Appears in 2 contracts
Sources: Construction Manager at Risk Construction Agreement, Construction Manager at Risk Construction Contract
Partial Occupancy. 20.1.1 Owner reserves the right to enter and install equipment within each portion of the Project as it is ready to receive same, upon the condition that ▇▇▇▇ shall not be responsible for equipment so placed other than loss or damage caused by the acts or omissions of ▇▇▇▇ or those in ▇▇▇▇'▇ employ. Such partial occupancy by Owner shall not constitute acceptance of the Project or of work not completed in accordance with the Contract Documents, nor shall it in any way relieve ▇▇▇▇ from correcting defective workmanship or materials in the area where Owner has installed equipment.
20.1.2 Owner reserves the right to take possession of or use all or part of any work prior to completion and final acceptance of all the work. If Owner exercises this right, ▇▇▇▇ shall be relieved of liability for loss or damage to completed portions of the work other than loss or damage caused by the acts, omissions, or breaches of warranty by ▇▇▇▇. Such taking of possession by Owner shall not relieve ▇▇▇▇ from any other provisions of the Contract Documents, shall not constitute a final acceptance of any such work or of work not completed in accordance with the Contract Documents, and shall not relieve ▇▇▇▇ from responsibility for correcting defective workmanship or materials in the area so occupied.
20.1.3 Owner may at any time during the performance of the work enter the work area for the purpose of performing any necessary work by Owner labor or other contractors, and for any other purpose in connection with the installation of facilities. In doing so, Owner shall endeavor not to interfere with ▇▇▇▇, and ▇▇▇▇ shall not interfere with other work being done by or on behalf of Owner.
Appears in 2 contracts
Sources: Construction Contract, Construction Contract
Partial Occupancy. 20.1.1 17.7.1 Owner reserves the right to enter and install equipment within each portion of the Project as it is ready to receive same, upon the condition that ▇▇▇▇ D-BE shall not be responsible for equipment so placed other than loss or damage caused by the acts or omissions of ▇▇▇▇ D-BE or those in ▇▇▇▇'▇ D-BE's employ. Such partial occupancy by Owner shall not constitute acceptance of the Project or of work not completed in accordance with the Contract Documents, nor shall it in any way relieve ▇▇▇▇ D-BE from correcting defective workmanship or materials in the area where Owner has installed equipment.
20.1.2 17.7.2 Owner reserves the right to take possession of or use all or part of any work prior to completion and final acceptance of all the work. If Owner exercises this right, ▇▇▇▇ D-BE shall be relieved of liability for loss or damage to completed portions of the work other than loss or damage caused by the acts, omissions, or breaches of warranty by ▇▇▇▇D-BE. Such taking of possession by Owner shall not relieve ▇▇▇▇ D-BE from any other provisions of the Contract Documents, shall not constitute a final acceptance of any such work or of work not completed in accordance with the Contract Documents, and shall not relieve ▇▇▇▇ D-BE from responsibility for correcting defective workmanship or materials in the area so occupied.
20.1.3 17.7.3 Owner may at any time during the performance of the work enter the work area for the purpose of performing any necessary work by Owner labor or other contractorsD-BEs, and for any other purpose in connection with the installation of facilities. In doing so, Owner shall endeavor not to interfere with ▇▇▇▇D-BE, and ▇▇▇▇ D-BE shall not interfere with other work being done by or on behalf of Owner.
Appears in 1 contract
Sources: Design and Construction Agreement
Partial Occupancy. 20.1.1 17.1.1. Owner reserves the right to enter and install equipment within each portion of the Project as it is ready to receive same, upon the condition that ▇▇▇▇ shall not be responsible for equipment so placed other than loss or damage caused by the acts or omissions of ▇▇▇▇ or those in ▇▇▇▇'▇ employ. Such partial occupancy by Owner shall not constitute acceptance of the Project or of work not completed in accordance with the Contract Documents, nor shall it in any way relieve ▇▇▇▇ from correcting defective workmanship or materials in the area where Owner has installed equipment.
20.1.2 17.1.2. Owner reserves the right to take possession of or use all or part of any work prior to completion and final acceptance of all the work. If Owner exercises this right, ▇▇▇▇ shall be relieved of liability for loss or damage to completed portions of the work other than loss or damage caused by the acts, omissions, or breaches of warranty by ▇▇▇▇. Such taking of possession by Owner shall not relieve ▇▇▇▇ from any other provisions of the Contract Documents, shall not constitute a final acceptance of any such work or of work not completed in accordance with the Contract Documents, and shall not relieve ▇▇▇▇ from responsibility for correcting defective workmanship or materials in the area so occupied.
20.1.3 17.1.3. Owner may at any time during the performance of the work enter the work area for the purpose of performing any necessary work by Owner labor or other contractorsCMARs, and for any other purpose in connection with the installation of facilities. In doing so, Owner shall endeavor not to interfere with ▇▇▇▇, and ▇▇▇▇ shall not interfere with other work being done by or on behalf of Owner.