Common use of Payment Schedule and Associated ITCC Clause in Contracts

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the costs expected to be incurred for the Distribution Upgrades, Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 Within 30 Calendar Days for Effective Date $190,200 $0 $0 $0 $0 $190,200 $66,570 Total $190,200 $0 $0 $0 $0 $190,200 $66,570 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $190,200 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $0 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0 Transmission credits pursuant to Section 9 of this Attachment 2 = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Attachment 2. In-Service Date: August 31, 2014 Critical milestones and responsibility as agreed to by the Parties: (a) Submit proof of insurance coverage in accordance with Article 8.1 of the GIA Interconnection Customer Within ten (10) calendar days after the Effective Date (b) Submittal of Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider pursuant to Section 10 of Attachment 2 of the GIA Interconnection Customer Within thirty (30) calendar days after the Effective Date (c) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Section 11 of Attachment 2 of the GIA Interconnection Customer Within thirty (30) calendar days after the Effective Date (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address for the project, 3) public right-of- way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer Within thirty (30) calendar days after the Effective Date (e) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Distribution Provider Within ninety (90) calendar days of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Customer Within sixty (60) calendar days after the Distribution Provider provides the design for the Civil Construction to the Interconnection Customer (h) Submittal of final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including system protection facilities, to the Distribution Provider Interconnection Customer At least ninety (90) calendar days prior to completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades (i) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within forty-five (45) calendar days following the Interconnection Customer’s submittal of the final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspection

Appears in 1 contract

Sources: Generator Interconnection Agreement

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the monthly incurred costs expected to be incurred for the Distribution Upgrades, Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 Within 30 Calendar Days for Effective Date $190,200 $0 $0 $0 $0 $190,200 $66,570 Total $190,200 $0 $0 $0 $0 $190,200 $66,570 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $190,200 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $1,407,359 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) =$0 Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) =$4,008,336 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0 1,266,201 Transmission credits pursuant to Section 9 of this Attachment 2 Appendix A = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 1,266,201 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Attachment Appendix A. 1. The Interconnection Customer’s Selected Option: Pursuant to Article 5.1 of the CLGIA, the Interconnection Customer has selected the Standard Option. 2. In-Service Date: August 31, 2014 Critical milestones and responsibility as agreed to by the PartiesMilestone Dates: (a) Submit proof of insurance coverage in accordance with Article 8.1 18.3 of the GIA CLGIA Interconnection Customer Within ten (10) calendar days Calendar Days after the Effective Date (b) Submittal of written authorization to proceed with design and procurement of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider, in accordance with Article 5.5.2 of the CLGIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (c) Submittal of second posting of Distribution Provider’s Distribution Upgrades to the Distribution Provider, pursuant to Section 8 of the CLGIP and Section 10 of Appendix A of the CLGIA Interconnection Customer June 21, 2013 (d) Submittal of third posting of Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider Provider, pursuant to Section 8 of the CLGIP and Section 10 of Attachment 2 Appendix A of the GIA CLGIA Interconnection Customer On or before the start of construction of Network Upgrades or Distribution Provider’s Interconnection Facilities (whichever is earlier). August 1, 2013 (e) Submittal of written authorization to proceed with construction to the Distribution Provider, pursuant to Article 5.6.3 of the CLGIA Interconnection Customer Within thirty (30) calendar days Calendar Days after the Effective Date (cf) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Article 5.17.3 and Section 11 of Attachment 2 Appendix A of the GIA CLGIA Interconnection Customer Within thirty (30) calendar days Calendar Days after the Effective Date (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address for the project, 3) public right-of- way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer Within thirty (30) calendar days after the Effective Date (eg) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Network Upgrades Distribution Provider Within ninety (9024) calendar days of Distribution Provider’s receipt of months following the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Customer Within sixty (60) calendar days after the Distribution Provider provides the design for the Civil Construction to the Interconnection CustomerEffective Date* (h) Submittal of final initial specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including system protection facilitiesSystem Protection Facilities, to the Distribution Provider Provider, pursuant to Article 5.10.1 of the CLGIA Interconnection Customer At least ninety one hundred eighty (90180) calendar days Calendar Days prior to completion the Initial Synchronization Date (i) Submittal of initial information including the Distribution Provider’s Transmission System information necessary to allow the Interconnection FacilitiesCustomer to select equipment, in accordance with Article 24.2 of the CLGIA Distribution Upgrades, and Network UpgradesProvider At least one hundred eighty (180) Calendar Days prior to Trial Operation (ij) Submittal of updated information by the Interconnection Customer, including manufacturer information, in accordance with Article 24.3 of the CLGIA Interconnection Customer No later than one hundred eighty (180) Calendar Days prior to Trial Operation (k) Review of and comment on the Interconnection Customer’s final specifications initial specifications, pursuant to Article 5.10.1 of the CLGIA Distribution Provider Within forty-five thirty (4530) calendar days following Calendar Days after the Interconnection Customer’s submittal submission of the final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspectioninitial specifications

Appears in 1 contract

Sources: Clustering Large Generator Interconnection Agreement (Clgia)

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the costs expected to be incurred for the Distribution Upgrades, Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 Within 30 thirty (30) Calendar Days for after the Effective Date $190,200 86,900 $0 $0 $0 $0 $190,200 86,900 $66,570 30,415 Total $190,200 86,900 $0 $0 $0 $0 $190,200 86,900 $66,570 30,415 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $190,200 86,900 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $0 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0 Transmission credits pursuant to Section 9 of this Attachment 2 = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Attachment 2. In-Service Date: August 31May 1, 2014 2016 Critical milestones and responsibility as agreed to by the Parties: (a) Submit proof of insurance coverage in accordance with Article 8.1 of the GIA Interconnection Customer Within ten (10) calendar days after the Effective Date (b) Submittal of Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider pursuant to Section 10 of Attachment 2 of the GIA Interconnection Customer Within thirty (30) calendar days after the Effective DateN/A (c) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Section 11 of Attachment 2 of the GIA Interconnection Customer Within thirty (30) calendar days after the Effective Date (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address for the project, 3) public right-of- way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer Within thirty (30) calendar days after the Effective Date (e) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Distribution Provider Within ninety (90) calendar days of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Customer Within sixty (60) calendar days after the Distribution Provider provides the design for the Civil Construction to the Interconnection Customer. Construction of SCE’s facilities does not commence until this milestone is completed; if the Customer can complete it earlier, then SCE’s completion under milestone (o) can also be earlier (h) Submittal of final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including system protection facilities, to the Distribution Provider Interconnection Customer At least ninety (90) calendar days prior to completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades (i) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within forty-five (45) calendar days following the Interconnection Customer’s submittal of the final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspection (k) Submission of a written test report to the Distribution Provider, in accordance with Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days following completion of Interconnection Customer’s testing and inspection (l) Written acknowledgement of Interconnection Customer’s Interconnection Facilities written test report pursuant to Article 2.1.2 of the GIA Distribution Provider Within five (5) Business Days of Interconnection Customer’s submission of the test report (m) Submission of written documentation reflecting Interconnection Customer’s satisfaction of parallel operation requirements pursuant to Article 2.2.2 of the GIA Interconnection Customer At least fifteen (15) calendar days prior to the Initial Synchronization Date (n) Proposed Interconnection Customer’s Interconnection Facilities completion date Interconnection Customer April 20, 2016 (o) Completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Distribution Provider Within (9) months following the Effective Date, assuming Items (d) and (g) of this Attachment 4 have occurred timely* (p) Notification of Interconnection Customer’s intention to begin on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA Interconnection Customer Ten (10) Business Days prior to Interconnection Customer’s verification testing date (q) Provide the ISO written notice that the required Distribution Provider facilities have been installed and tested, and that initial synchronization of the Generating Facility to the Distribution System is expected to occur on the Initial Synchronization Date Distribution Provider At least ten (10) calendar days prior to the Initial Synchronization Date (r) Performance of a complete calibration test and functional trip test of the system protection facilities Interconnection Customer and Distribution Provider During the on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA, and prior to initial synchronization; for Fast Track Projects this milestone is completed during the commissioning test (s) In-Service Date Interconnection Customer May 1, 2016 (t) Proposed Initial Synchronization Date Interconnection Customer May 10, 2016 (u) Distribution Provider’s written authorization authorizing Interconnection Customer to operate its Generating Facility in parallel with the Distribution Provider’s Distribution System, pursuant to Article 2.2.2 of the GIA Distribution Provider Within five (5) calendar days after the Initial Synchronization Date and the Interconnection Customer’s satisfaction of parallel operation requirements pursuant to Article 2.2.2

Appears in 1 contract

Sources: Generator Interconnection Agreement

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the monthly incurred costs expected to be incurred for the new Distribution Upgrades, Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date Customer- Financed Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 Within 30 Calendar Days for calendar days of the Effective Date $190,200 168,000 $0 $0 $0 $0 $190,200 168,000 $66,570 58,800 Total $190,200 168,000 $0 $0 $0 $0 $190,200 168,000 $66,570 58,800 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $190,200 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $0 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) =$0 Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) =$168,000 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Transmission credits pursuant to Section 9 of this Attachment 2 Appendix A = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 Payment for the installation of existing facilities was made by the Interconnection Customer under the IFA. *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Attachment 2Appendix A. 18. In-Service Date: August 31Review of Generating Facility and Interconnection Customer’s Interconnection Facilities Design. Pursuant to Article 5.10 of this GIA, 2014 Critical milestones and responsibility as agreed to by the Parties: (a) Submit proof of insurance coverage in accordance with Article 8.1 of the GIA Interconnection Customer Within ten (10) calendar days within 120 Calendar Days after the Effective Date (b) Submittal , the Interconnection Customer shall provide all drawings, specifications, information and documents related to the Generating Facility and Interconnection Customer’s Interconnection Facilities necessary for the Distribution Provider to verify the compatibility of Credit Support for the Generating Facility and Interconnection Customer’s Interconnection Facilities with the Distribution Provider’s Interconnection Facilities, Distribution Upgrades System and Network Upgrades to Transmission System, and compliance with the Distribution Provider pursuant to Section 10 of Attachment 2 Interconnection Handbook. Such drawings, specifications, information and documents shall include, but are not limited to: i) an electrical one-line diagram of the GIA Generating Facility and Interconnection Customer Within thirty (30Customer’s Interconnection Facilities; ii) calendar days after the Effective Date (c) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Section 11 of Attachment 2 an electrical three-line diagram of the GIA Interconnection Customer Within thirty (30) calendar days after the Effective Date (d) Provide the following information (“Required Information”) in support of the Distribution ProviderCustomer’s engineering protective relays and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address devices used for the project, 3) public right-of- way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer Within thirty (30) calendar days after the Effective Date (e) Completion of the Distribution Provider’s design and engineering protection of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, System and the Civil Construction Distribution Provider Within ninety (90Transmission System; iii) calendar days electrical elementary or wiring diagrams of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work ’s protective relays and design devices used for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering protection of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, System and Civil Construction (gTransmission System; iv) Completion protection settings of the Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Customer Within sixty (60) calendar days after the Distribution Provider provides the design for the Civil Construction to the Interconnection Customer (h) Submittal of final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including system relays or other protective devices used for protection facilities, to the Distribution Provider Interconnection Customer At least ninety (90) calendar days prior to completion of the Distribution Provider’s Interconnection Facilities, Distribution UpgradesSystem and Transmission System, and Network Upgrades (i) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within forty-five (45) calendar days following the Interconnection Customer’s submittal including a test report for such relays or other protective devices dated within 5 years of the final specifications for Effective Date; and v) a plot plan of the Generating Facility and Interconnection Customer’s Interconnection Facilities Facilities. Such drawings, specifications, information and documents submitted by the Interconnection Customer to the Distribution Provider must be certified in writing by a professional engineer registered in the State of California, or other qualified and authorized representative of the Interconnection Customer, as being current and accurate representations of the Generating Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspectionFacilities.

Appears in 1 contract

Sources: Generator Interconnection Agreement (Gia)

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the monthly incurred costs expected to be incurred for the Distribution Upgrades, Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date Within 30 calendar days of the Effective Date Interconnection Facilities Cost $143,700 Distribution Upgrades Cost $0 Reliability Network Upgrades Cost $0 Delivery Network Upgrades Cost $0 One- Time Cost $0 Project Payment $143,700 Associated ITCC* 1 Within 30 Calendar Days for Effective Date $190,200 $0 $0 $0 $0 $190,200 $66,570 Total $190,200 $0 $0 $0 $0 $190,200 $66,570 50,300 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $190,200 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $0 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) =$0 Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) =$143,700 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Transmission credits pursuant to Section 9 of this Attachment 2 = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Attachment 2. One-line Diagram Depicting the Small Generating Facility, Interconnection Facilities, Metering Equipment, and Upgrades In-Service Date: August May 31, 2014 2013 Critical milestones and responsibility as agreed to by the Parties:: Item Milestone Responsible Party Due Date (a) Submit proof of insurance coverage in accordance with Article 8.1 of the GIA SGIA Interconnection Customer Within ten (10) calendar days after of the Effective Date execution of this SGIA (b) Submittal of Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider pursuant to Section 10 of Attachment 2 of the GIA Interconnection Customer Within thirty (30) calendar days after the Effective Date (c) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Section 11 of Attachment 2 of the GIA SGIA Interconnection Customer Within thirty (30) calendar days after of the Effective Date Date (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address for the project, 3) public right-of- way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer Within thirty (30) calendar days after the Effective Date (e) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Distribution Provider Within ninety (90) calendar days of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Customer Within sixty (60) calendar days after the Distribution Provider provides the design for the Civil Construction to the Interconnection Customer (hc) Submittal of final initial specifications for the Interconnection Customer’s Interconnection Facilities and Small Generating Facility, including system protection facilities, to the Distribution Provider Interconnection Customer At least ninety Within (9030) calendar days prior to completion of the Distribution Provider’s Effective Date (d) Submittal of payment number 1 pursuant to Section 17 of Attachment 2 of the SGIA Interconnection FacilitiesCustomer Within thirty (30) calendar days of the Effective Date (e) Provide panel drawings, Distribution Upgradeseasements/lease agreements, grading plans, sewer and Network Upgrades storm plot plans, landscape, sprinkler and pedestal locations (i“Required Information”) Interconnection Customer Within thirty (30) calendar days of the Effective Date (f) Review of and comment on the Interconnection Customer’s final initial specifications Distribution Provider Within forty-five thirty (4530) calendar days following of the Interconnection Customer’s submittal submission of the final initial specifications for the Interconnection Customer(g) Design of Distribution Provider’s Interconnection Facilities and Generating Facility Distribution Upgrades Distribution Provider Within sixty (j60) Notification business days following the Effective Date assuming Item (e) of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspectionthis Attachment 4 has occurred timely

Appears in 1 contract

Sources: Small Generator Interconnection Agreement (Sgia)