Penalty for Non-Conforming Design Documents. Should the Total Program Manager submit drawings, plans, specifications or other documents or materials for review as required herein that are deemed unacceptable as defined by the terms “Revise and Resubmit” by the plan review authority (Building Department, Design Services Department, Peer Plan Review Consultant) the costs as determined by the SBBC, for subsequent reviews after the second submittal for that Phase shall be borne by the Total Program Manager and the SBBC will deduct such costs from the Total Program Manager’s Basic Services Fee.
Appears in 2 contracts
Sources: Total Program Management Agreement, Total Program Manager Agreement