Common use of Period of Compensable Delay, Suspension, or Interruption Clause in Contracts

Period of Compensable Delay, Suspension, or Interruption. The length and extent of compensable delay shall be determined by ascertaining the number of additional days to the Contract Time that are needed to perform the Work. This determination shall be made in accordance with the Contract Documents and after County’s receipt of the written notice under Subsection 10.3.1.

Appears in 3 contracts

Sources: Construction Agreement, Construction Agreement, Construction Agreement

Period of Compensable Delay, Suspension, or Interruption. The length and extent of compensable delay shall be determined by ascertaining the number of additional days to the Contract Time that are needed to perform the Work. This determination shall be made in accordance with the Contract Documents documents and after County’s receipt of the written notice under Subsection 10.3.1.

Appears in 3 contracts

Sources: Fixed Price Construction Contract, Fixed Price Construction Contract, Fixed Price Construction Contract