The "Physical Condition of Site" clause defines the responsibility for assessing and understanding the actual state of the project site before work begins. Typically, it requires the contractor to inspect the site and verify its conditions, such as soil quality, access, and existing structures, prior to commencing construction. This clause ensures that any unforeseen site issues are identified early, allocating the risk of unknown conditions and preventing disputes over site-related delays or additional costs.
Physical Condition of Site. Prior to the expiration of the Developer’s Due Diligence Period, Developer shall not have elected to cancel Escrow and terminate this Agreement due to the physical condition of the Site and shall have delivered Developer’s Notice to Proceed to Agency pursuant to Section 303.3 of this Agreement.
Physical Condition of Site. Developer shall approve or disapprove of the physical condition of the Site within Developer’s Due Diligence Period. Developer’s approval of the physical condition of the Site shall be both an Agency’s and a Developer’s Condition Precedent to the Closing. If Developer, based upon Developer’s Soils and Engineering Reports, disapproves of the physical condition of the Site, then Developer may, in Developer’s sole discretion, terminate the Escrow and this Agreement by written Notice to Agency.‌
Physical Condition of Site. Buyer shall not have elected to cancel Escrow and terminate this Agreement due to the physical condition of the Site pursuant to Section 202.3 hereof.
Physical Condition of Site. During the Contingency Period, the District shall be satisfied, in its reasonable discretion, with the physical condition of each Identified School Site, including, without limitation, the results of soil tests (including borings), toxic and hazardous waste studies, wetlands information, geotechnical studies, surveys, engineering, historical use, traffic and access studies, structural studies and review of zoning, fire, safety and other compliance matters.
Physical Condition of Site. Prior to the expiration of the Developer’s Due Diligence Period, Developer shall not
Physical Condition of Site 

Related to Physical Condition of Site

  • Physical Condition Except as disclosed in the Physical Conditions Reports delivered to Lender in connecting with this Loan, to Borrower's knowledge, the Property, including, without limitation, all buildings, improvements, parking facilities, sidewalks, storm drainage systems, roofs, plumbing systems, HVAC systems, fire protection systems, electrical systems, equipment, elevators, exterior sidings and doors, landscaping, irrigation systems and all structural components, are in good condition, order and repair in all material respects; there exists no structural or other material defects or damages in the Property, whether latent or otherwise, and Borrower has not received notice from any insurance company or bonding company of any defects or inadequacies in the Property, or any part thereof, which would adversely affect the insurability of the same or cause the imposition of extraordinary premiums or charges thereon or of any termination or threatened termination of any policy of insurance or bond.

  • Environmental Condition Except as set forth on Schedule 4.11, (a) to Borrower’s knowledge, no Loan Party’s nor any of its Subsidiaries’ properties or assets has ever been used by a Loan Party, its Subsidiaries, or by previous owners or operators in the disposal of, or to produce, store, handle, treat, release, or transport, any Hazardous Materials, where such disposal, production, storage, handling, treatment, release or transport was in violation, in any material respect, of any applicable Environmental Law, (b) to Borrower’s knowledge, after due inquiry, no Loan Party’s nor any of its Subsidiaries’ properties or assets has ever been designated or identified in any manner pursuant to any environmental protection statute as a Hazardous Materials disposal site, (c) no Loan Party nor any of its Subsidiaries has received notice that a Lien arising under any Environmental Law has attached to any revenues or to any Real Property owned or operated by a Loan Party or its Subsidiaries, and (d) no Loan Party nor any of its Subsidiaries nor any of their respective facilities or operations is subject to any outstanding written order, consent decree, or settlement agreement with any Person relating to any Environmental Law or Environmental Liability that, individually or in the aggregate, could reasonably be expected to result in a Material Adverse Effect.

  • Protection of Site from encroachments On and after signing the memorandum and/or subsequent memorandum referred to in Clause 8.2, and until the issue of the Completion Certificate, the Contractor shall maintain a round-the-clock ▇▇▇▇▇ over the Site and shall ensure and procure that no encroachment takes place thereon. During the Construction Period, the Contractor shall protect the Site from any and all occupations, encroachments or Encumbrances, and shall not place or create nor permit any Sub-contractor or other person claiming through or under the Agreement to place or create any Encumbrance or security threat over all or any part of the Site or the Project Assets, or on any rights of the Contractor therein or under this Agreement, save and except as otherwise expressly set forth in this Agreement. In the event of any encroachment or occupation on any part of the Site, the Contractor shall report such encroachment or occupation forthwith to the Authority and undertake its removal at its own cost and expenses.

  • Special Condition With respect to Liability to the Fund or its shareholders, and subject to applicable state and federal law, the Board Member shall be indemnified pursuant to this Section 1 against any Liability unless such Liability arises by reason of the Board Member’s willful misfeasance, bad faith, gross negligence, or reckless disregard of the duties involved in the conduct of his or her office as defined in such Section 17(h) of the Investment Company Act of 1940, as amended (“Disabling Conduct”).

  • Environmental Conditions A Phase I environmental site assessment (or update of a previous Phase I and or Phase II environmental site assessment) and, with respect to certain Mortgage Loans, a Phase II environmental site assessment (collectively, an “ESA”) meeting ASTM requirements conducted by a reputable environmental consultant in connection with such Mortgage Loan within 12 months prior to its origination date (or an update of a previous ESA was prepared), and such ESA (i) did not identify the existence of recognized environmental conditions (as such term is defined in ASTM E1527-13 or its successor, hereinafter “Environmental Condition”) at the related Mortgaged Property or the need for further investigation, or (ii) if the existence of an Environmental Condition or need for further investigation was indicated in any such ESA, then at least one of the following statements is true: (A) an amount reasonably estimated by a reputable environmental consultant to be sufficient to cover the estimated cost to cure any material noncompliance with applicable Environmental Laws or the Environmental Condition has been escrowed by the related Mortgagor and is held or controlled by the related Mortgagee; (B) if the only Environmental Condition relates to the presence of asbestos-containing materials, radon in indoor air, lead based paint or lead in drinking water, the only recommended action in the ESA is the institution of such a plan, an operations or maintenance plan has been required to be instituted by the related Mortgagor that can reasonably be expected to mitigate the identified risk; (C) the Environmental Condition identified in the related environmental report was remediated or abated in all material respects prior to the date hereof, and, if and as appropriate, a no further action or closure letter was obtained from the applicable governmental regulatory authority (or the environmental issue affecting the related Mortgaged Property was otherwise listed by such governmental authority as “closed” or a reputable environmental consultant has concluded that no further action is required); (D) an environmental policy or a lender’s pollution legal liability insurance policy that covers liability for the identified circumstance or condition was obtained from an insurer rated no less than “A-” (or the equivalent) by ▇▇▇▇▇’▇ Investors Service, Inc., S&P Global Ratings, acting through Standard & Poor’s Financial Services LLC, Fitch Ratings, Inc. and/or A.M. Best Company; (E) a party not related to the Mortgagor was identified as the responsible party for such condition or circumstance and such responsible party has financial resources reasonably estimated to be adequate to address the situation; or (F) a party related to the Mortgagor having financial resources reasonably estimated to be adequate to address the situation is required to take action. To the Mortgage Loan Seller’s knowledge, except as set forth in the ESA, there is no Environmental Condition (as such term is defined in ASTM E1527-13 or its successor) at the related Mortgaged Property.