Planned Completion Sample Clauses

The Planned Completion clause defines the expected date or timeframe by which a project, service, or deliverable should be finished. It typically specifies a target completion date and may outline the responsibilities of the parties to meet this deadline, as well as procedures for addressing delays or extensions. This clause ensures that all parties have a clear understanding of the project's timeline, helping to manage expectations and reduce the risk of disputes related to scheduling.
Planned Completion. All interfaces required from the Employer and others. • The dates when the Contractor plans to complete work allowing the Employer and others to do their work. • Provisions for float and time risk allowance. • The dates when the Contractor will need access to a part of the site, acceptance and Plant and Material and other things to be provided by the Employer. • Access to site will be on 04 January 2016 but the actual start date of the works will be determined by National Control, the Employer will give notice of 24 hours. In addition to the above information the Contractor shows the following information on each revised programme: • The actual progress achieved as well as the forecast for the remaining work. • The effect of implemented compensation events and of notified early warning matters. • How the Contractor plans to deal with any delays and to correct notified Defects. • Take note that, the revised programme should be submitted to the Employer within 1 day after any change has occurred.
Planned Completion. May 2011)
Planned Completion.  All interfaces required from the Employer and others.  The dates when the Contractor plans to complete work allowing the Employer and others to do their work.  Provisions for float and time risk allowance.  The dates when the Contractor will need access to a part of the site, acceptance and Plant and Material and other things to be provided by the Employer. In addition to the above information the Contractor shows the following information on each revised programme:  The actual progress achieved as well as the forecast for the remaining work.  The effect of implemented compensation events and of notified early warning matters.  How the Contractor plans to deal with any delays and to correct notified Defects.

Related to Planned Completion

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.