Planning Data. (1) Participant shall timely report to ERCOT those items and conditions necessary for ERCOT’s internal planning and compliance with ERCOT’s guidelines in effect from time to time. The information supplied must include, without limitation, the following: (a) Current Operating Plan (COP) for each hour of the next Operating Day submitted by 0600 in the Day-Ahead; (b) Revised COP reflecting changes in the hourly availability of the RMR Unit as soon as reasonably practical, but in no event later than 60 minutes after the event that caused the change; and (c) Status of the RMR Unit with respect to environmental limitations, if any. If any of the specified environmental limitations will be exceeded by ERCOT’s planned or actual use of the RMR Unit Participant shall provide ERCOT with as much advance written notice as is reasonably possible. (2) ERCOT and Participant shall timely coordinate with each other on the status of the RMR Unit with respect to Operational Limitations.
Appears in 2 contracts
Sources: Reliability Must Run Agreement, Reliability Must Run Agreement
Planning Data. (1) Participant shall timely report to ERCOT those items and conditions necessary for ERCOT’s internal planning and compliance with ERCOT’s guidelines in effect from time to time. The information supplied must include, without limitation, the following:
(a) Current Operating Availability Plan (COP) for each hour of the next Operating Day submitted by 0600 in of the Day-Aheadpreceding day;
(b) Revised COP Availability Plan reflecting changes in the hourly availability of the RMR Unit as soon as reasonably practical, but in no event later than 60 minutes after the event that caused the change; and
(c) Status of the RMR Unit with respect to environmental limitationsEnvironmental Limitations listed in Section 1(H) above, if any. If any of the specified environmental limitations Environmental Limitations will be exceeded by ERCOT’s planned or actual use of the RMR Unit Participant shall provide ERCOT with as much advance written notice as is reasonably possible.
(2) ERCOT and Participant shall timely coordinate with each other on the status of the RMR Unit with respect to Operational Limitations.
Appears in 1 contract
Sources: Reliability Must Run Agreement