Points of nonconformance with Project Schedule. noted. In each monthly Progress and Completion Schedule, Design-Builder shall graphically note and highlight key critical path activities and Milestone Dates that were not met historically and/or will not be met under the proposed Progress and Completion Schedule.
Appears in 3 contracts
Sources: Standard Form of Agreement, Design Build Agreement, Construction Contract