Common use of Power System Stabilizers Clause in Contracts

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and the provisions of Section 4.6.5.1

Appears in 54 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, Council and in accordance with the provisions of Section 4.6.5.1

Appears in 36 contracts

Sources: Standard Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers power system stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve the right to reasonably establish minimum acceptable settings for any installed power system stabilizers, subject to the design and operating limitations of the provisions Generating Facility. If the Generating Facility’s power system stabilizers are removed from service or are not capable of Section 4.6.5.1automatic operation,

Appears in 20 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers power system stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and the provisions of Section 4.6.5.1procedures

Appears in 14 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers power system stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, . Transmission Provider and Transmission Owner reserve the provisions of Section 4.6.5.1right to reasonably establish minimum acceptable

Appears in 5 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider reserves the right to reasonably establish minimum acceptable settings for any installed Power System Stabilizers, subject to the design and operating limitations of the provisions of Section 4.6.5.1Generating Facility. If the Generating Facility's Power System Stabilizers are removed

Appears in 2 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and the provisions of Section 4.6.5.1Applicable

Appears in 2 contracts

Sources: Iso Service Agreement No. 1774, Large Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, Council and in accordance with the provisions of Section 4.6.5.14.6.5.1 of the CAISO Tariff. The CAISO reserves the right to establish reasonable minimum acceptable settings for any installed Power System Stabilizers, subject to the design and operating limitations of the Large Generating

Appears in 2 contracts

Sources: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and the provisions of Section 4.6.5.1the

Appears in 2 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and the provisions of Section 4.6.5.1guidelines

Appears in 1 contract

Sources: Jea Agreement for Generator Interconnection to Transmission System (Jagits)

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and in accordance with the provisions of Section 4.6.5.14.6.5.1 of the ISO Tariff. Distribution Provider reserves the right to reasonably establish minimum acceptable

Appears in 1 contract

Sources: Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and the provisions of Section 4.6.5.1Reliability

Appears in 1 contract

Sources: Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines published and procedures established current Minimum Technical Requirements published by PREPA. If the Applicable Reliability Council, and the provisions of Section 4.6.5.1Large Generating

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement (Lgia)

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Electric Reliability Council, Organization and in accordance with the provisions of Section 4.6.5.1

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement (Lgia)

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and the provisions of Section 4.6.5.1. Transmission Provider

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and in accordance with the provisions of Section 4.6.5.14.6.5.1 of the ISO Tariff. Distribution Provider reserves the right to reasonably establish minimum acceptable settings for any installed Power System Stabilizers, subject to the design and operating limitations of the Generating Facility. If the Generating Facility’s Power System

Appears in 1 contract

Sources: Generator Interconnection Agreement (Gia)

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate Power System Stabilizers in accordance with Applicable Reliability Standards, the guidelines and procedures established by the Applicable Reliability Council, and in accordance with the provisions of Section 4.6.5.1

Appears in 1 contract

Sources: Generator Interconnection Agreement