Common use of Power System Stabilizers Clause in Contracts

Power System Stabilizers. Interconnection Customer shall procure, install, maintain and operate power system stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve the right to reasonably establish minimum acceptable settings for any installed power system stabilizers, subject to the design and operating limitations of the Generating Facility. If the Generating Facility’s power system stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission Provider’s system operator, or its designated representative. The requirements of this paragraph shall not apply to induction generators.

Appears in 32 contracts

Sources: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia), Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Large Generating Facility. If the Large Generating Facility’s power system stabilizers 's Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission Provider’s 's system operator, or its designated representative. The requirements of this paragraph shall not apply to induction wind generators.

Appears in 27 contracts

Sources: Surplus Large Generator Interconnection Agreement, Surplus Large Generator Interconnection Agreement, Agreement to Amend Surplus Large Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Generating Facility. If the Generating Facility’s power system stabilizers 's Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission ProviderOwner’s system operator, or its designated representative. The requirements of this paragraph shall not apply to induction wind generators.

Appears in 10 contracts

Sources: Settlement Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Large Generating Facility. If the Large Generating Facility’s power system stabilizers Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission Provider’s system operator, or its designated representative. The requirements of this paragraph shall not apply to induction wind generators.

Appears in 9 contracts

Sources: Small Generator Interconnection Agreement (Sgia), Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement (Lgia)

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve the right to reasonably establish minimum acceptable settings for any installed power system stabilizers, subject to the design and operating limitations of the Generating Facility. If the Generating Facility’s power system stabilizers are removed from service or are not capable of automatic operation, the Interconnection Customer shall immediately notify the Transmission Provider’s system operator, or its designated representative. The requirements of this paragraph shall not apply to induction generators.

Appears in 8 contracts

Sources: Large Generator Interconnection Agreement (ITC Holdings Corp.), Generator Interconnection Agreement, Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Large Generating Facility. If the Large Generating Facility’s power system stabilizers 's Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission Provider’s 's system operator, or its designated representative. The requirements of this paragraph shall not apply to induction generators.wind generators.‌

Appears in 7 contracts

Sources: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability CouncilStandards. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Generating Facility. If the Generating Facility’s power system stabilizers 's Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission Provider’s 's system operator, or its designated representative. The requirements of this paragraph shall not apply to induction wind generators.

Appears in 5 contracts

Sources: Standard Generator Interconnection Agreement (Sgia), Standard Generator Interconnection Agreement (Sgia), Standard Generator Interconnection Agreement (Sgia)

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Large Generating Facility. If the Large Generating Facility’s power system stabilizers 's Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission ProviderOwner’s system operator, or its designated representative. The requirements of this paragraph shall not apply to induction wind generators.

Appears in 4 contracts

Sources: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Generating Facility. If the Generating Facility’s power system stabilizers 's Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission ProviderOwner’s system operator, or its designated representative. The requirements of this paragraph shall not apply to induction non-synchronous generators.

Appears in 3 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Interim Generator Interconnection Agreement

Power System Stabilizers. Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Electric Reliability CouncilCouncilOrganization. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Large Generating Facility. If the Large Generating Facility’s power system stabilizers 's Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission Provider’s 's system operator, or its designated representative. The requirements of this paragraph shall not apply to induction wind generators.

Appears in 2 contracts

Sources: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers, which includes synchronous machines, in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve Operating Agent reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Generating Facility. If the Generating Facility’s power system stabilizers Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission ProviderOperating Agent’s system operator, or its designated representative. The requirements of this paragraph shall not apply to induction inverted based generators.

Appears in 1 contract

Sources: Large Generator Interconnection Agreement (Lgia)

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability CouncilStandards. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Large Generating Facility. If the Large Generating Facility’s power system stabilizers 's Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission Provider’s 's system operator, or its designated representative. The requirements of this paragraph shall not apply to induction wind generators.

Appears in 1 contract

Sources: Large Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers, which includes synchronous machines, in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve Operating Agent reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Generating Facility. If the Generating Facility’s power system stabilizers Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission ProviderOperating Agent’s system operator, or its designated representative. The requirements of this paragraph shall not apply to induction inverter based generators.

Appears in 1 contract

Sources: Large Generator Interconnection Agreement

Power System Stabilizers. The Interconnection Customer shall procure, install, maintain and operate power system stabilizers Power System Stabilizers in accordance with the guidelines and procedures established by the Applicable Reliability Council. Transmission Provider and Transmission Owner reserve reserves the right to reasonably establish minimum acceptable settings for any installed power system stabilizersPower System Stabilizers, subject to the design and operating limitations of the Generating Facility. If the Generating Facility’s power system stabilizers 's Power System Stabilizers are removed from service or are not capable of automatic operation, Interconnection Customer shall immediately notify the Transmission Provider’s 's system operator, or its designated representative. The requirements of this paragraph shall not apply to induction wind generators.

Appears in 1 contract

Sources: Generator Interconnection Agreement