PRE-COMPLETION COMMISSIONING AND COMPLETION46 Clause Samples

The 'Pre-Completion Commissioning and Completion' clause defines the procedures and requirements for testing and verifying that a project or facility is ready for use before it is officially completed. This typically involves a series of inspections, performance tests, and documentation reviews to ensure all systems and components function as intended and meet contractual standards. For example, equipment may be operated under simulated conditions to confirm proper installation and operation. The core function of this clause is to ensure that any issues are identified and resolved prior to handover, thereby reducing the risk of defects and disputes after completion.
PRE-COMPLETION COMMISSIONING AND COMPLETION46. 17.1 Not less than [six (6)] months before the Completion Date [and the Post Completion Works Date], D&B Co shall provide the Authority with a draft of the Final Commissioning Programme in respect of the Works relative thereto, as jointly developed by the Authority and D&B Co in accordance with the provisions of Clause 17.2 and 17.3 (Pre-Completion Commissioning and Completion) and Schedule 10 (Outline Commissioning Programme). The Authority shall provide D&B Co with comments on the draft Final Commissioning Programme submitted to it within [fifteen (15)] Business Days. The parties shall, within [fifteen (15)] Business Days of receipt by D&B Co of the Authority's comments agree the terms of the Final Commissioning Programme provided that the Authority may by prior notice to D&B Co change the scope and time of the Authority's Commissioning or the Authority's Post Completion Commissioning and reimburse D&B Co its 46 The Template Education D&B Agreement assumes the Authority and D&B Co will each undertake inspection and commissioning activities both prior to and after completion. Parties need to consider which commissioning activities have to occur before and which after completion (and, in each case, by whom) on a project specific basis. In the case of schools projects, the approach to commissioning that is to be followed should be set out in an outline commissioning programme in Appendix A of Schedule 10 (Outline Commissioning Programme). Broadly it is envisaged that the drafting of this Schedule will follow the same approach as has been taken to schedule 10 of the Template MIM Education PA. The Template Education D&B Agreement envisages that the Final Commissioning Programme(s) will set out all requirements and obligations in relation to the development, nature, principles and performance of the completion tests to be performed to enable certification of completion to take place. Parties need to consider which commissioning activities have to occur before and which after completion (and, in each case, by whom) on a project specific basis on further education college projects in particular. Template drafting has been provided here for Post Completion Works, to be used where relevant. Authorities will need to consider whether further project specific drafting is required, including amendments to accommodate multi-facility projects where relevant. reasonable costs incurred as a result of such change in scope or time of the Authority's Commissioning. If the pa...
PRE-COMPLETION COMMISSIONING AND COMPLETION46. 17.1 Not less than [six (6)] months before the Completion Date [and the Post Completion Works Date], D&B Co shall provide the Authority with a draft of the Final Commissioning Programme in respect of the Works relative thereto, as jointly developed by the Authority and D&B Co in accordance with the provisions of Clause 17.2 and 17.3 (Pre-Completion Commissioning and Completion) and Schedule 10 (Outline Commissioning Programme). The Authority shall provide D&B Co with comments on the draft Final Commissioning Programme submitted to it within [fifteen (15)] Business Days. The parties shall, within [fifteen (15)] Business Days of receipt by D&B Co of the Authority's comments agree the terms of the Final Commissioning Programme provided that the Authority may by prior notice to D&B Co change the scope and time of the Authority's Commissioning or the Authority's Post Completion Commissioning and reimburse D&B Co its reasonable costs incurred as a result of such change in scope or time of the Authority's Commissioning. If the parties are unable to agree the Final

Related to PRE-COMPLETION COMMISSIONING AND COMPLETION46

  • Synchronization, Commissioning and Commercial Operation 5.1.1 The SPG shall give PGVCL at least thirty (30) days’ advanced preliminary written notice and at least fifteen (15) days’ advanced final written notice, of the date on which it intends to synchronize the Solar Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the SPG to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the SPG at its generation facility of the Power Project at its own cost. The SPG shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substation/ and checking/verification is made by the concerned authorities of the PGVCL. 5.1.4 The SPG shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the SPG will inject in-firm power to grid from time to time to carry out operational/ functional test prior to commercial operation. For avoidance of doubt, it is clarified that Synchronization / Connectivity of the Project with the grid shall not to be considered as Commissioning of the Project. 5.1.5 The SPG shall commission the Project within nine (9) Months from the Date of execution of this PPA. Declaration of COD shall be certified by the commissioning committee. 5.1.6 The Parties agree that for the purpose of commencement of the supply of electricity by SPG to PGVCL, liquidated damages for delay etc., the Scheduled Commissioning Date as defined in this Agreement shall be the relevant date.

  • PROGRESS AND COMPLETION 8.2.1 All time limits stated in the Contract Documents are material terms and time is the essence of the Contract. A failure by Contractor to do what is required by the time specified in the Contract Documents is a breach of the contract. 8.2.2 The Contractor shall begin the Work on the date of commencement as defined in 8.2.3 If in the sole opinion of the State, the Contractor fails to commence work on the project or to complete the work of said project within the time specified above, or to prosecute the work in such a manner that it appears that the completion date can be assured, the State shall have the right to notify the Contractor by Certified Mail that the terms of the Contract have been violated, and that effective immediately the Contract is terminated and the State has the right to and in fact is taking over and attending to completion of the project without prejudice to the State's remedies for any losses sustained

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:

  • Construction Completion The related Construction shall have been completed substantially in accordance with the related Plans and Specifications, the related Deed and all Applicable Laws, and such Leased Property shall be ready for occupancy and operation. All fixtures, equipment and other property contemplated under the Plans and Specifications to be incorporated into or installed in such Leased Property shall have been substantially incorporated or installed, free and clear of all Liens except for Permitted Liens.

  • Commissioning Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.