PROGRESS AND COMPLETION Clause Samples

The "Progress and Completion" clause sets out the obligations and expectations regarding the timely advancement and finalization of work under a contract. It typically requires the contractor to perform tasks according to a specified schedule, meet key milestones, and complete the project by an agreed deadline. This clause ensures that both parties have a clear understanding of the timeline, helping to prevent delays and disputes by holding the contractor accountable for steady progress and on-time delivery.
POPULAR SAMPLE Copied 3 times
PROGRESS AND COMPLETION. 8.2.1 All time limits stated in the Contract Documents are material terms and time is the essence of the Contract. A failure by Contractor to do what is required by the time specified in the Contract Documents is a breach of the contract. 8.2.2 The Contractor shall begin the Work on the date of commencement as defined in 8.2.3 If in the sole opinion of the State, the Contractor fails to commence work on the project or to complete the work of said project within the time specified above, or to prosecute the work in such a manner that it appears that the completion date can be assured, the State shall have the right to notify the Contractor by Certified Mail that the terms of the Contract have been violated, and that effective immediately the Contract is terminated and the State has the right to and in fact is taking over and attending to completion of the project without prejudice to the State's remedies for any losses sustained
PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
PROGRESS AND COMPLETION. 4.2.2, 8.2, 9.8, 9.9.1, 14.1.4, 15.1.4 9.3, 9.6, 9.8.5, 9.10.3, 14.2.3, 15.1.4
PROGRESS AND COMPLETION. Time limits stated in the Contract Documents are of the essence of this Agreement. By executing the Agreement, the Design/Builder confirms that the Contract Time is a reasonable period of time for achieving Substantial Completion of the Work. Design/Builder agrees to have all work substantially completed NOT LATER THAN, March 1, 2004.
PROGRESS AND COMPLETION. § 8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing the Agreement, the Contractor confirms that the Contract Time is a reasonable period for performing the Work. § 8.2.2 The Contractor shall not knowingly, except by agreement or instruction of the Owner in writing, commence the Work prior to the effective date of insurance required to be furnished by the Contractor and Owner. § 8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve Substantial Completion within the Contract Time.
PROGRESS AND COMPLETION. 15.4.1 Time of the Essence Time limits stated in the Contract Documents are of the essence to the Contract Documents. By executing the Facilities Lease, Developer confirms that the Contract Time is a reasonable period for performing the Work.
PROGRESS AND COMPLETION. ‌ 8.2.1 Contractor agrees that the Contract Time is reasonable for performing the Work and that Contractor is able to perform the Work within the Contract Time. .1 The Construction Schedule may reflect a period of performance that is shorter than the Contract Time; provided however, that the difference shall be deemed as float and nothing in this Paragraph or in any other provision of the Contract Documents shall be construed as creating any contractual right, express or implied, on the part of Contractor to finish the Project earlier than the Contract Time and under no circumstances shall City be liable to Contractor for any costs, damages or compensation due to the inability of Contractor to complete the Work earlier than the Contract Time, regardless of the cause, including, without limitation, acts or omissions (intentional or negligent) of City. .2 Contractor has included in its Bid price the costs of all Contractor and Subcontractor overhead (direct and indirect) for the entire duration of the Contract Time. The above costs are included in Contractor’s Bid notwithstanding Contractor's anticipation of completion in fewer days than established by the Contract Time. .3 No increase in the Contract Sum shall be made or granted for Delay if Contractor completes the Work before expiration of the Contract Time. .4 No reduction in the Contract Sum shall be made nor will Contractor be required to remain on the Project Site if the Work is completed before expiration of the Contract Time. .5 The Construction Manager will schedule and hold weekly progress meetings and other meetings to be required by progress of the Work as determined by the Construction Manager. Contractor and/or Contractor's designee shall be present at each meeting. Contractor may also be required to request attendance by representatives of Contractor’s suppliers, manufacturers and Subcontractors. 8.2.2 Except by agreement or instruction of City in writing, Contractor shall not commence operations on the Site or elsewhere prior to the effective date of insurance required by Article 11 to be furnished by Contractor. Contractor’s obligations to commence the Work and to complete the Work within the Contract Time shall not be changed by the effective date of such insurance. 8.2.3 Contractor shall proceed expeditiously with adequate forces and shall achieve Final Completion within the Contract Time. If City determines and notifies Contractor that Contractor’s progress is such that Contractor will n...
PROGRESS AND COMPLETION. It is expressly understood by the Contractor and Owner that time is important in the performance of this Agreement. The Contractor shall begin the Work on the date of commencement set forth in the written notice to proceed. The Contractor shall carry the Work forward expeditiously with adequate forces and shall complete it in accordance with the Schedule.
PROGRESS AND COMPLETION. It is expressly understood by the Supplier that TIME IS OF THE ESSENCE in the performance of this Agreement. The Supplier shall begin the work on the date of commencement set forth in the Agreement. The Supplier shall carry the work forward expeditiously with adequate forces and shall complete it by the time work is to be completed as stated in the Agreement. If the Supplier is delayed at any time in the progress of the work, written notice thereof, including an explanation of the cause and the anticipated duration of the delay, shall be given promptly to the Customer by the Supplier, but in no event later than five (5) days after such delay becomes apparent. Failure to give such notice promptly and within such time limit shall be deemed sufficient reason for denial by Customer of an extension of time for performance and may be deemed a default. Failure of Supplier's subcontractor or materials and equipment suppliers to meet schedules shall not be cause for an extension of time. Supplier acknowledges that it has sole responsibility for expediting the efforts of its subcontractors, suppliers, and others. Without prejudice to other remedies that Customer may have under the Agreement or the law, if Supplier fails to meet the time schedule or other delivery date obligations set forth in the Agreement (the “Guaranteed Delivery Dates”), then Supplier shall pay to Customer as liquidated damages for such delay, and not as a penalty, the amounts set forth in the applicable Agreement, if any, for each day the delivery is late under the applicable Agreement (the “Liquidated Damages”). If the Agreement does not establish an amount, the amount of the Liquidated Damages shall be equal to one per cent (1%) of the Contract Price for each full calendar week's delay. Such Delay Damages shall never exceed fifteen per cent (15%) of the Contract Price. The Parties acknowledge and agree that because of the unique nature of the performance it is difficult or impossible to determine with precision the amount of damages that would or might be incurred by Customer as a result of Supplier's failure to meet the Guaranteed Delivery Dates under the applicable Agreement, Statement of Work, or applicable order. It is understood and agreed by the Parties that (i) Customer shall be disadvantaged by failure of Supplier to meet such obligations,
PROGRESS AND COMPLETION. CONTRACTOR shall commence work on the services to be performed upon full execution of this Agreement and shall consider full execution of this Agreement as Notice to Proceed. All services shall be completed as mutually agreed upon by both parties; deviations from the schedule shall be approved by VCTC. Progress reports, which include a summary of work completed during the billing period, will be provided by the CONTRACTOR with each invoice.