Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be: 1. Permits and applicable regulations as may be provided by law or that govern the site;
Appears in 3 contracts
Sources: Contract, Contract, Construction Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Amendments and Change Orders;
3. Contract;
4. Addenda and Bulletins;
5. Supplementary General Conditions;
Appears in 2 contracts
Sources: Construction Phase Services, Construction Phase Services
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Use of Contingency or Change Orders - in inverse chronological order, and in the same order as specific portions they are modifying (i.e., later-issued language shall take precedence and prevail over earlier conflicting versions or language).
3. Contract;
4. Supplemental General Conditions;
5. General Conditions;
Appears in 2 contracts
Sources: Construction Contract, Construction Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Amendments and Change Orders;
3. Contract;
4. Addenda and Bulletins;
5. Supplementary General Conditions;
6. General Conditions;
Appears in 1 contract
Sources: Construction Services Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Amendments and Change Orders;
3. Agreement;
4. Bid, as accepted by County;
5. Addenda and Bulletins;
6. Special Provisions;
Appears in 1 contract
Sources: Construction Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Use of Contingency or Change Orders - in inverse chronological order, and in the same order as specific portions they are modifying (i.e., later-issued language shall take precedence and prevail over earlier conflicting versions or language);
3. Contract;
Appears in 1 contract
Sources: Construction Contract