Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be: 1. Permits and applicable regulations as may be provided by law or that govern the site;

Appears in 3 contracts

Sources: Contract, Contract, Construction Contract

Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be: 1. Permits and applicable regulations as may be provided by law or that govern the site; 2. Amendments and Change Orders; 3. Contract; 4. Addenda and Bulletins; 5. Supplementary General Conditions;

Appears in 2 contracts

Sources: Construction Phase Services, Construction Phase Services

Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be: 1. Permits and applicable regulations as may be provided by law or that govern the site; 2. Use of Contingency or Change Orders - in inverse chronological order, and in the same order as specific portions they are modifying (i.e., later-issued language shall take precedence and prevail over earlier conflicting versions or language). 3. Contract; 4. Supplemental General Conditions; 5. General Conditions;

Appears in 2 contracts

Sources: Construction Contract, Construction Contract

Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be: 1. Permits and applicable regulations as may be provided by law or that govern the site; 2. Amendments and Change Orders; 3. Contract; 4. Addenda and Bulletins; 5. Supplementary General Conditions; 6. General Conditions;

Appears in 1 contract

Sources: Construction Services Contract

Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be: 1. Permits and applicable regulations as may be provided by law or that govern the site; 2. Amendments and Change Orders; 3. Agreement; 4. Bid, as accepted by County; 5. Addenda and Bulletins; 6. Special Provisions;

Appears in 1 contract

Sources: Construction Contract

Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be: 1. Permits and applicable regulations as may be provided by law or that govern the site; 2. Use of Contingency or Change Orders - in inverse chronological order, and in the same order as specific portions they are modifying (i.e., later-issued language shall take precedence and prevail over earlier conflicting versions or language); 3. Contract;

Appears in 1 contract

Sources: Construction Contract